ITAC Assessment: ME0292
ITAC logo
ITAC Assessment: ME0292
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Various hardwood products
NAICS
n/a
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 65,000
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $104,121 954,572
kWh
Electricity Demand $30,441 3,456
kW-mo/yr
LPG $60,213 10,492
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,587 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,172

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings By-product Production Savings
01 2.1321: Replace fossil fuel equipment with electrical equipment $13,365 $13,000 $(-1,187.0)
(-15,826)
kWh
- $14,552
-
MMBtu
- - - -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,056 $26,450 $6,516
86,753
kWh
$3,540
-
kW-mo/yr
- - - - -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $6,527 $9,000 $7,401
98,769
kWh
$1,405
-
kW-mo/yr
$(-2,279.0)
-
MMBtu
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,822 $340 $2,822
37,515
kWh
- - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,944 $5,571 $1,351
17,878
kWh
$593
-
kW-mo/yr
- - - - -
06 2.4133: Use most efficient type of electric motors $1,025 $1,373 $531
7,034
kWh
$494
-
kW-mo/yr
- - - - -
07 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $827 $250 $827
11,137
kWh
- - - - - -
08 2.7492: Use proper thickness of insulation on building envelope $310 $240 - - $310
-
MMBtu
- - - -
09 2.4221: Install compressor air intakes in coolest locations $264 $380 $264
3,517
kWh
- - - - - -
10 2.2123: Insulate feedwater tank $173 $183 - - $173
-
MMBtu
- - - -
11 2.2515: Use optimum thickness insulation $34 $72 - - $34
-
MMBtu
- - - -
12 3.5315: Lease / purchase baler; sell cardboard to recycler $8,700 $9,500 - - - $8,700
-
lb
- - -
13 3.6125: Sell combustible waste $4,000 $12,000 - - - - - - $4,000
14 3.6192: Use a less expensive method of waste removal $40 - - - - - $40
-
lb
- -
15 4.513: Re-arrange equipment layout to reduce labor costs $2,500 $1,550 - - - - - $2,500 -
TOTAL RECOMMENDED $52,587 $79,909 $18,525
246,777
kWh
$6,032
-
kW-mo/yr
$12,790
-
MMBtu
$8,700
-
lb
$40
-
lb
$2,500 $4,000
TOTAL IMPLEMENTED $3,172 $580 $2,822
37,515
kWh
- $310
-
MMBtu
- $40
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs