| Assessment Year | 2000 |
|---|---|
| Principal Product | Various hardwood products |
| NAICS |
n/a
|
| SIC | 2426: Hardwood Dimension and Flooring Mills |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
65,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $104,121 | 954,572 |
kWh
|
$0.11 |
| Electricity Demand | $30,441 | 3,456 |
kW-mo/yr
|
$8.81 |
| LPG | $60,213 | 10,492 |
MMBtu
|
$5.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $52,587 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,172 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $13,365 | $13,000 |
$(-1,187.0)
(-15,826)
kWh
|
- |
$14,552
-
MMBtu
|
- | - | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,056 | $26,450 |
$6,516
86,753
kWh
|
$3,540
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,527 | $9,000 |
$7,401
98,769
kWh
|
$1,405
-
kW-mo/yr
|
$(-2,279.0)
-
MMBtu
|
- | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,822 | $340 |
$2,822
37,515
kWh
|
- | - | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,944 | $5,571 |
$1,351
17,878
kWh
|
$593
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,025 | $1,373 |
$531
7,034
kWh
|
$494
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $827 | $250 |
$827
11,137
kWh
|
- | - | - | - | - | - | |
| 08 | 2.7492: Use proper thickness of insulation on building envelope | $310 | $240 | - | - |
$310
-
MMBtu
|
- | - | - | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $264 | $380 |
$264
3,517
kWh
|
- | - | - | - | - | - | |
| 10 | 2.2123: Insulate feedwater tank | $173 | $183 | - | - |
$173
-
MMBtu
|
- | - | - | - | |
| 11 | 2.2515: Use optimum thickness insulation | $34 | $72 | - | - |
$34
-
MMBtu
|
- | - | - | - | |
| 12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $8,700 | $9,500 | - | - | - |
$8,700
-
lb
|
- | - | - | |
| 13 | 3.6125: Sell combustible waste | $4,000 | $12,000 | - | - | - | - | - | - | $4,000 | |
| 14 | 3.6192: Use a less expensive method of waste removal | $40 | - | - | - | - | - |
$40
-
lb
|
- | - | |
| 15 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,500 | $1,550 | - | - | - | - | - | $2,500 | - | |
| TOTAL RECOMMENDED | $52,587 | $79,909 |
$18,525
246,777
kWh
|
$6,032
-
kW-mo/yr
|
$12,790
-
MMBtu
|
$8,700
-
lb
|
$40
-
lb
|
$2,500 | $4,000 | ||
| TOTAL IMPLEMENTED | $3,172 | $580 |
$2,822
37,515
kWh
|
- |
$310
-
MMBtu
|
- |
$40
-
lb
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs