Assessment Year | 2000 |
---|---|
Principal Product | Athletic Shoes |
NAICS |
n/a
|
SIC | 3144: Women's Footwear, Except Athletic |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
120,300
ft2
|
Annual Production | 864,000
pieces
|
Production Hrs. Annual | 4,120
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,780 | 1,668,816 |
kWh
|
$0.062 |
Electricity Demand | $67,549 | 5,987 |
kW-mo/yr
|
$11.28 |
Electricity Fees | $1,117 | - |
|
- |
Fuel Oil #2 | $17,241 | 4,862 |
MMBtu
|
$3.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $96,286 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,671 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $16,377 | - | - | - | $16,377 | - | - | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $6,781 | $15,835 |
$8,836
144,490
kWh
|
- | - | - |
$(-2,055.0)
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,432 | $590 |
$6,432
107,268
kWh
|
- | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,482 | $14,072 |
$3,046
50,703
kWh
|
$2,436
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.2136: Install / repair insulation on steam lines | $4,832 | $9,423 |
$4,832
300,117
kWh
|
- | - | - | - | - | - | |
06 | 2.5196: Use small number of high output units instead of many small inefficient units | $3,459 | $10,000 |
$2,393
39,859
kWh
|
$1,066
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,023 | $3,500 |
$7,928
132,181
kWh
|
- | - |
$(-4,905.0)
-
MMBtu
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $1,525 | $2,000 |
$1,525
24,912
kWh
|
- | - | - | - | - | - | |
09 | 3.5217: Reuse / recycle/ sell paper products | $46,375 | - | - | - | - | - | - |
$46,375
-
lb
|
- | |
10 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,000 | $3,500 | - | - | - | - | - | - | $2,000 | |
TOTAL RECOMMENDED | $96,286 | $58,920 |
$34,992
799,530
kWh
|
$3,502
-
kW-mo/yr
|
$16,377 |
$(-4,905.0)
-
MMBtu
|
$(-2,055.0)
-
MMBtu
|
$46,375
-
lb
|
$2,000 | ||
TOTAL IMPLEMENTED | $37,671 | $29,585 |
$23,763
615,181
kWh
|
$2,436
-
kW-mo/yr
|
$16,377 |
$(-4,905.0)
-
MMBtu
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs