ITAC Assessment: ME0283
ITAC logo
ITAC Assessment: ME0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Brushes
NAICS
n/a
SIC 3991: Brooms and Brushes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 75,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 6,000
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $116,123 1,012,603
kWh
Electricity Demand $21,146 2,775
kW-mo/yr
Natural Gas $5,611 774
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,741 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,855

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Primary Product Savings
01 4.445: Install equipment to move product $20,000 $130 - - - - $20,000
02 2.5196: Use small number of high output units instead of many small inefficient units $8,241 $10,900 $7,050
78,253
kWh
$1,191
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $1,561 $500 - - $1,561
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $1,294 $300 $1,294
14,361
kWh
- - - -
05 2.4239: Eliminate or reduce compressed air usage $792 $210 $792
879
kWh
- - - -
06 3.4155: Meter waste water $853 - - - - $853
-
Tgal
-
TOTAL RECOMMENDED $32,741 $12,040 $9,136
93,493
kWh
$1,191
-
kW-mo/yr
$1,561
-
MMBtu
$853
-
Tgal
$20,000
TOTAL IMPLEMENTED $2,855 $800 $1,294
14,361
kWh
- $1,561
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs