ITAC Assessment: ME0274
ITAC logo
ITAC Assessment: ME0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Low Carbon Steel Castings
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 84
Plant Area 111,000
ft2
Annual Production 1,925
ton
Production Hrs. Annual 2,110
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $772,669 8,695,194
kWh
Electricity Fees $83,377 -
LPG $133,075 27,178
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $72,172 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Water Consumption Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $27,426 $27,050 n/a - - - - $27,426 -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,039 $14,259 n/a $14,316
204,572
kWh
$(-4,277.0)
-
MMBtu
- - - -
03 2.2437: Recover waste heat from equipment $5,786 $14,670 n/a $5,786
346,131
kWh
- - - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,882 $825 n/a $5,538
79,132
kWh
$(-1,656.0)
-
MMBtu
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,789 $7,571 n/a $2,789
39,859
kWh
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $3,182 $500 n/a $3,182
45,428
kWh
- - - - -
07 2.2614: Use cooling tower or economizer to replace chiller cooling $371 $980 n/a $371
5,275
kWh
- - - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $470 $100 n/a $470
6,741
kWh
- - - - -
09 3.1161: Eliminate/reduce an operation $16,433 $2,400 n/a $3,503
50,117
kWh
$6,064
-
MMBtu
- $6,866
-
lb
- -
10 3.4151: Minimize water usage $1,674 $868 n/a $1,176
16,706
kWh
- $246
-
Tgal
- - $252
-
Tgal
11 3.4151: Minimize water usage $120 $85 n/a $84
1,172
kWh
- $18
-
Tgal
- - $18
-
Tgal
TOTAL RECOMMENDED $72,172 $69,308 $37,215
795,133
kWh
$131
-
MMBtu
$264
-
Tgal
$6,866
-
lb
$27,426 $270
-
Tgal
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs