| Assessment Year | 1999 |
|---|---|
| Principal Product | pine boards |
| NAICS |
n/a
|
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $5 M to 10M |
| # of Employees | 45 |
| Plant Area |
59,000
ft2
|
| Annual Production | 3,750,000
thousand feet
|
| Production Hrs. Annual | 2,312
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $201,261 | 3,037,515 |
kWh
|
$0.066 |
| Electricity Demand | $62,431 | 9,262 |
kW-mo/yr
|
$6.74 |
| Electricity Fees | $1,159 | - |
|
- |
| Wood | $39,168 | 52,224 |
MMBtu
|
$0.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,707 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,276 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,060 | $47,675 |
$27,060
410,023
kWh
|
- | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,694 | $11,058 |
$2,585
39,273
kWh
|
$1,109
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,248 | $150 |
$1,248
18,757
kWh
|
- | - | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $731 | $1,580 |
$505
12,309
kWh
|
$226
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.2511: Insulate bare equipment | $366 | $407 | - | - |
$366
-
MMBtu
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $224 | $100 |
$224
3,517
kWh
|
- | - | - | - | - | |
| 07 | 3.4151: Minimize water usage | $8,700 | $6,800 |
$(-300.0)
(-3,517)
kWh
|
- | - | - | - |
$9,000
-
Tgal
|
|
| 08 | 3.3113: Use other methods for neutralization | $6,000 | $7,800 | - | - | - | - | $6,000 | - | |
| 09 | 3.4155: Meter waste water | $1,684 | $200 | - | - | - |
$1,684
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $49,707 | $75,770 |
$31,322
480,362
kWh
|
$1,335
-
kW-mo/yr
|
$366
-
MMBtu
|
$1,684
-
gal
|
$6,000 |
$9,000
-
Tgal
|
||
| TOTAL IMPLEMENTED | $34,276 | $59,590 |
$31,117
471,570
kWh
|
$1,109
-
kW-mo/yr
|
$366
-
MMBtu
|
$1,684
-
gal
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs