ITAC Assessment: ME0269
ITAC logo
ITAC Assessment: ME0269
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Woolen goods
NAICS
n/a
SIC 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing)
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 400,000
ft2
Annual Production 2,700,000
pieces
Production Hrs. Annual 6,600
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $891,857 10,594,080
kWh
Electricity Demand $236,066 31,061
kW-mo/yr
Electricity Fees $47,911 -
Fuel Oil #6 $115,056 51,175
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $113,775 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $70,822

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Fuel Oil #6 Savings Solid Waste (non-haz) Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $24,778 $56,288 $20,400
242,966
kWh
$4,378
-
kW-mo/yr
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,324 $1,000 $16,324
194,314
kWh
- - - - -
03 4.114: Add/modify equipment to improve drying process $12,357 $32,660 - - - $12,357
-
MMBtu
- -
04 2.2511: Insulate bare equipment $11,193 $6,570 - - - $11,193
-
MMBtu
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,299 $10,600 $8,299
98,769
kWh
- - - - -
06 2.2444: Use hot process fluids to preheat incoming process fluids $6,530 $21,460 - - - $6,530
-
MMBtu
- -
07 2.4133: Use most efficient type of electric motors $6,202 $10,069 $5,518
65,651
kWh
$684
-
kW-mo/yr
- - - -
08 2.2511: Insulate bare equipment $4,461 $650 - - - $4,461
-
MMBtu
- -
09 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,296 $5,114 $1,741
20,809
kWh
$755
-
kW-mo/yr
$(-200.0)
-
MMBtu
- - -
10 2.6218: Turn off equipment when not in use $2,179 $2,000 $2,179
25,791
kWh
- - - - -
11 2.4221: Install compressor air intakes in coolest locations $1,837 $800 $1,837
21,981
kWh
- - - - -
12 2.4239: Eliminate or reduce compressed air usage $1,273 $1,632 $1,498
27,550
kWh
$(-225.0)
-
kW-mo/yr
- - - -
13 2.2511: Insulate bare equipment $547 $273 - - - $547
-
MMBtu
- -
14 3.5311: Recover and reuse waste material $15,270 - - - - - $15,270
-
lb
-
15 3.4151: Minimize water usage $229 $100 - - - - - $229
-
Tgal
TOTAL RECOMMENDED $113,775 $149,216 $57,796
697,831
kWh
$5,592
-
kW-mo/yr
$(-200.0)
-
MMBtu
$35,088
-
MMBtu
$15,270
-
lb
$229
-
Tgal
TOTAL IMPLEMENTED $70,822 $104,072 $54,218
655,041
kWh
$4,837
-
kW-mo/yr
- $11,538
-
MMBtu
- $229
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Fuel Oil #6 Savings Solid Waste (non-haz) Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs