ITAC Assessment: ME0266
ITAC logo
ITAC Assessment: ME0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product French Fries
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 42,209
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 1,820
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $104,506 2,281,360
kWh
Electricity Demand $99,351 11,505
kW-mo/yr
Electricity Fees $7,515 -
Fuel Oil #2 $48,079 13,258
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,805 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,614

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2628: Utilize a less expensive cooling method $26,281 $10,500 $16,744
239,156
kWh
$9,537
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,510 $6,708 $3,782
53,927
kWh
$728
-
kW-mo/yr
- - -
03 4.821: Pay bills on time to avoid late fees $4,072 - - - - - $4,072
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,186 $5,825 $1,757
25,205
kWh
$844
-
kW-mo/yr
$(-415.0)
-
MMBtu
- -
05 2.2628: Utilize a less expensive cooling method $1,914 $6,370 $1,914
27,257
kWh
- - - -
06 2.2135: Repair and eliminate steam leaks $1,176 $100 - - $1,176
-
MMBtu
- -
07 2.2437: Recover waste heat from equipment $740 $1,490 - - $740
-
MMBtu
- -
08 2.2121: Increase amount of condensate returned $636 $610 $(-12.0)
(-293)
kWh
- $648
-
MMBtu
- -
09 2.2136: Install / repair insulation on steam lines $401 $85 - - $401
-
MMBtu
- -
10 2.4221: Install compressor air intakes in coolest locations $277 $190 $277
4,103
kWh
- - - -
11 3.7214: Reduce or eliminate waste $1,612 $300 - - - $1,612
-
lb
-
TOTAL RECOMMENDED $43,805 $32,178 $24,462
349,355
kWh
$11,109
-
kW-mo/yr
$2,550
-
MMBtu
$1,612
-
lb
$4,072
TOTAL IMPLEMENTED $41,614 $25,618 $22,271
317,995
kWh
$11,109
-
kW-mo/yr
$2,550
-
MMBtu
$1,612
-
lb
$4,072
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs