Assessment Year | 1999 |
---|---|
Principal Product | French Fries |
NAICS |
n/a
|
SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
Sales Range | $1 M to 5M |
# of Employees | 20 |
Plant Area |
42,209
ft2
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 1,820
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $104,506 | 2,281,360 |
kWh
|
$0.046 |
Electricity Demand | $99,351 | 11,505 |
kW-mo/yr
|
$8.64 |
Electricity Fees | $7,515 | - |
|
- |
Fuel Oil #2 | $48,079 | 13,258 |
MMBtu
|
$3.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $41,614 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $26,281 | $10,500 |
$16,744
239,156
kWh
|
$9,537
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,510 | $6,708 |
$3,782
53,927
kWh
|
$728
-
kW-mo/yr
|
- | - | - | |
03 | 4.821: Pay bills on time to avoid late fees | $4,072 | - | - | - | - | - | $4,072 | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,186 | $5,825 |
$1,757
25,205
kWh
|
$844
-
kW-mo/yr
|
$(-415.0)
-
MMBtu
|
- | - | |
05 | 2.2628: Utilize a less expensive cooling method | $1,914 | $6,370 |
$1,914
27,257
kWh
|
- | - | - | - | |
06 | 2.2135: Repair and eliminate steam leaks | $1,176 | $100 | - | - |
$1,176
-
MMBtu
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $740 | $1,490 | - | - |
$740
-
MMBtu
|
- | - | |
08 | 2.2121: Increase amount of condensate returned | $636 | $610 |
$(-12.0)
(-293)
kWh
|
- |
$648
-
MMBtu
|
- | - | |
09 | 2.2136: Install / repair insulation on steam lines | $401 | $85 | - | - |
$401
-
MMBtu
|
- | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $277 | $190 |
$277
4,103
kWh
|
- | - | - | - | |
11 | 3.7214: Reduce or eliminate waste | $1,612 | $300 | - | - | - |
$1,612
-
lb
|
- | |
TOTAL RECOMMENDED | $43,805 | $32,178 |
$24,462
349,355
kWh
|
$11,109
-
kW-mo/yr
|
$2,550
-
MMBtu
|
$1,612
-
lb
|
$4,072 | ||
TOTAL IMPLEMENTED | $41,614 | $25,618 |
$22,271
317,995
kWh
|
$11,109
-
kW-mo/yr
|
$2,550
-
MMBtu
|
$1,612
-
lb
|
$4,072 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs