Assessment Year | 1999 |
---|---|
Principal Product | Impellers |
NAICS |
n/a
|
SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
Sales Range | $5 M to 10M |
# of Employees | 52 |
Plant Area |
25,600
ft2
|
Annual Production | 1,250
pieces
|
Production Hrs. Annual | 4,750
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,997 | 538,980 |
kWh
|
$0.095 |
Electricity Demand | $150,858 | 1,715 |
kW-mo/yr
|
$87.96 |
Electricity Fees | $1,129 | - |
|
- |
Natural Gas | $4,725 | 675 |
MMBtu
|
$7.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,253 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,828 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $7,332 | $5,655 |
$7,332
81,477
kWh
|
- | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,027 | $9,340 |
$1,605
17,878
kWh
|
$422
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $896 | - |
$896
9,965
kWh
|
- | - | - | - | - | - | |
04 | 2.8112: Combine utility meters | $456 | $230 | - | - | - | - | - | $456 | - | |
05 | 2.8112: Combine utility meters | $450 | $720 | - | - | - | - | - | $450 | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $370 | $1,000 |
$370
4,103
kWh
|
- | - | - | - | - | - | |
07 | 2.2437: Recover waste heat from equipment | $365 | $400 | - | - |
$365
-
MMBtu
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $285 | $215 |
$285
3,224
kWh
|
- | - | - | - | - | - | |
09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $14,100 | $955,000 | - | - | - |
$14,100
-
gal
|
- | - | - | |
10 | 4.652: Replace existing equipment with more suitable substitutes | $2,290 | $2,460 | - | - | - | - | - | $2,290 | - | |
11 | 3.8134: Use water-based cutting fluids to eliminate need for solvent cleaning | $917 | - | - | - | - |
$917
-
gal
|
- | - | - | |
12 | 3.7223: Install shrouding on machines to prevent splashing | $473 | $5,240 | - | - | - |
$473
-
gal
|
- | - | - | |
13 | 3.1191: Change procedures / equipment / operating conditions | $292 | - | - | - | - | - |
$80
-
lb
|
- | $212 | |
TOTAL RECOMMENDED | $30,253 | $980,260 |
$10,488
116,647
kWh
|
$422
-
kW-mo/yr
|
$365
-
MMBtu
|
$15,490
-
gal
|
$80
-
lb
|
$3,196 | $212 | ||
TOTAL IMPLEMENTED | $26,828 | $971,560 |
$10,118
112,544
kWh
|
$422
-
kW-mo/yr
|
$365
-
MMBtu
|
$15,017
-
gal
|
- | $906 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs