ITAC Assessment: ME0258
ITAC logo
ITAC Assessment: ME0258
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product laths
NAICS
n/a
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 20
Plant Area 31,613
ft2
Annual Production 18,764,150
pieces
Production Hrs. Annual 1,872
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,450 847,011
kWh
Electricity Demand $14,500 3,528
kW-mo/yr
Electricity Fees $428 -
LPG $1,032 125
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $205,174 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 4.425: Eliminate/reduce redundant inspections $75,000 $106,500 - - - - $75,000 - -
02 4.423: Move product using mechanical means $74,945 $21,400 - - - - - $74,945 -
03 3.5311: Recover and reuse waste material $20,000 $1,200 - - - - - - $20,000
04 2.6218: Turn off equipment when not in use $8,990 $295 - - $8,990 - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,192 $8,181 $1,782
21,102
kWh
$410
-
kW-mo/yr
- - - - -
06 4.444: Install system to collect scrap $1,300 $890 - - - - - - $1,300
07 2.4133: Use most efficient type of electric motors $715 $1,372 $715
7,327
kWh
- - - - - -
08 4.111: Add equipment/ operators to reduce production bottleneck $21,564 $47,350 - - - $21,564
-
lb
- - -
09 2.6231: Utilize controls to operate equipment only when needed $358 $1,855 - - - $358
-
lb
- - -
10 2.2511: Insulate bare equipment $110 $220 - - - $110
-
lb
- - -
TOTAL RECOMMENDED $205,174 $189,263 $2,497
28,429
kWh
$410
-
kW-mo/yr
$8,990 $22,032
-
lb
$75,000 $74,945 $21,300
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs