Assessment Year | 1999 |
---|---|
Principal Product | laths |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 20 |
Plant Area |
31,613
ft2
|
Annual Production | 18,764,150
pieces
|
Production Hrs. Annual | 1,872
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,450 | 847,011 |
kWh
|
$0.065 |
Electricity Demand | $14,500 | 3,528 |
kW-mo/yr
|
$4.11 |
Electricity Fees | $428 | - |
|
- |
LPG | $1,032 | 125 |
MMBtu
|
$8.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $205,174 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.425: Eliminate/reduce redundant inspections | $75,000 | $106,500 | - | - | - | - | $75,000 | - | - | |
02 | 4.423: Move product using mechanical means | $74,945 | $21,400 | - | - | - | - | - | $74,945 | - | |
03 | 3.5311: Recover and reuse waste material | $20,000 | $1,200 | - | - | - | - | - | - | $20,000 | |
04 | 2.6218: Turn off equipment when not in use | $8,990 | $295 | - | - | $8,990 | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,192 | $8,181 |
$1,782
21,102
kWh
|
$410
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 4.444: Install system to collect scrap | $1,300 | $890 | - | - | - | - | - | - | $1,300 | |
07 | 2.4133: Use most efficient type of electric motors | $715 | $1,372 |
$715
7,327
kWh
|
- | - | - | - | - | - | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $21,564 | $47,350 | - | - | - |
$21,564
-
lb
|
- | - | - | |
09 | 2.6231: Utilize controls to operate equipment only when needed | $358 | $1,855 | - | - | - |
$358
-
lb
|
- | - | - | |
10 | 2.2511: Insulate bare equipment | $110 | $220 | - | - | - |
$110
-
lb
|
- | - | - | |
TOTAL RECOMMENDED | $205,174 | $189,263 |
$2,497
28,429
kWh
|
$410
-
kW-mo/yr
|
$8,990 |
$22,032
-
lb
|
$75,000 | $74,945 | $21,300 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs