Assessment Year | 1998 |
---|---|
Principal Product | glass slides |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
95,000
ft2
|
Annual Production | 27,000,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $330,657 | 4,549,824 |
kWh
|
$0.073 |
Electricity Demand | $82,255 | 10,458 |
kW-mo/yr
|
$7.87 |
Electricity Fees | $5,258 | - |
|
- |
Natural Gas | $46,239 | 8,230 |
MMBtu
|
$5.62 |
LPG | $4,105 | 150 |
MMBtu
|
$27.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,986 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $47,993 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.612: Contract out maintenance | $32,242 | $75,900 |
$10,742
134,232
kWh
|
- | - | - | $21,500 | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $11,877 | $21,500 |
$13,524
168,816
kWh
|
$2,136
-
kW-mo/yr
|
$(-3,783.0)
-
MMBtu
|
- | - | |
03 | 4.231: Purchase equipment instead of leasing | $3,760 | $20,100 | - | - | - | - | $3,760 | |
04 | 2.4239: Eliminate or reduce compressed air usage | $2,503 | $12,300 |
$2,047
25,791
kWh
|
$456
-
kW-mo/yr
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $2,747 | $7,023 |
$2,297
28,722
kWh
|
$450
-
kW-mo/yr
|
- | - | - | |
06 | 4.211: Consider use / purchase of bulk materials where possible | $2,059 | $8,900 | - | - | - | - | $2,059 | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,060 | $3,860 |
$535
6,741
kWh
|
$1,686
-
kW-mo/yr
|
$(-161.0)
-
MMBtu
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $1,945 | $2,860 |
$1,945
79,426
kWh
|
- | - | - | - | |
09 | 3.4111: Use closed cycle process to minimize waste water production | $11,059 | $7,193 | - | - |
$4,944
-
MMBtu
|
$6,115
-
Tgal
|
- | |
10 | 3.4111: Use closed cycle process to minimize waste water production | $9,734 | $15,640 |
$(-309.0)
(-3,224)
kWh
|
- |
$4,385
-
MMBtu
|
$5,658
-
Tgal
|
- | |
TOTAL RECOMMENDED | $79,986 | $175,276 |
$30,781
440,504
kWh
|
$4,728
-
kW-mo/yr
|
$5,385
-
MMBtu
|
$11,773
-
Tgal
|
$27,319 | ||
TOTAL IMPLEMENTED | $47,993 | $92,976 |
$14,984
242,380
kWh
|
$450
-
kW-mo/yr
|
$4,944
-
MMBtu
|
$6,115
-
Tgal
|
$21,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs