| Assessment Year | 1998 |
|---|---|
| Principal Product | shoes |
| NAICS |
n/a
|
| SIC | 3144: Women's Footwear, Except Athletic |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
75,000
ft2
|
| Annual Production | 1,750,000
pieces
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $111,065 | 1,545,428 |
kWh
|
$0.072 |
| Electricity Demand | $59,765 | 6,388 |
kW-mo/yr
|
$9.36 |
| Electricity Fees | $5,076 | - |
|
- |
| LPG | $559 | 24 |
MMBtu
|
$23.29 |
| Fuel Oil #4 | $33,548 | 8,221 |
MMBtu
|
$4.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $89,328 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.212: Adopt in-house material generation | $33,500 | $25,500 | - | - | - | - | $33,500 | |
| 02 | 4.231: Purchase equipment instead of leasing | $4,122 | $16,460 | - | - | - | - | $4,122 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,100 | $600 |
$3,100
44,256
kWh
|
- | - | - | - | |
| 04 | 2.4234: Cool compressor air intake with heat exchanger | $1,398 | $500 |
$1,398
78,253
kWh
|
- | - | - | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,102 | $1,700 |
$879
9,086
kWh
|
$493
-
kW-mo/yr
|
$(-270.0)
-
MMBtu
|
- | - | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $360 | - |
$360
5,275
kWh
|
- | - | - | - | |
| 07 | 3.2176: Increase use of automation | $45,746 | $25,500 | - | - | - |
$45,746
-
gal
|
- | |
| 08 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $3,330 | $1,251 | - | - | - |
$3,330
-
gal
|
- | |
| TOTAL RECOMMENDED | $92,658 | $71,511 |
$5,737
136,870
kWh
|
$493
-
kW-mo/yr
|
$(-270.0)
-
MMBtu
|
$49,076
-
gal
|
$37,622 | ||
| TOTAL IMPLEMENTED | $89,328 | $70,260 |
$5,737
136,870
kWh
|
$493
-
kW-mo/yr
|
$(-270.0)
-
MMBtu
|
$45,746
-
gal
|
$37,622 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs