Assessment Year | 1998 |
---|---|
Principal Product | Electro Plating Silver |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
29,500
ft2
|
Annual Production | 8,500,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $134,488 | 1,937,866 |
kWh
|
$0.069 |
Electricity Demand | $43,312 | 12,531 |
kW-mo/yr
|
$3.46 |
Electricity Fees | $6,861 | - |
|
- |
Natural Gas | $66,221 | 9,879 |
MMBtu
|
$6.70 |
Fuel Oil #2 | $49,136 | 10,143 |
MMBtu
|
$4.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,201 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,576 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,696 | - |
$2,696
38,394
kWh
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,163 | $5,970 |
$1,561
22,274
kWh
|
$602
-
kW-mo/yr
|
- | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,398 | $400 |
$1,398
19,930
kWh
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,127 | $3,000 |
$1,127
16,120
kWh
|
- | - | - | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,051 | $2,000 |
$235
293
kWh
|
$918
-
kW-mo/yr
|
$(-102.0)
-
MMBtu
|
- | |
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $895 | $700 |
$590
8,499
kWh
|
$479
-
kW-mo/yr
|
- |
$(-174.0)
-
MMBtu
|
|
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $803 | $900 |
$293
4,103
kWh
|
$602
-
kW-mo/yr
|
- |
$(-92.0)
-
MMBtu
|
|
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $769 | $2,250 |
$769
11,137
kWh
|
- | - | - | |
09 | 2.2511: Insulate bare equipment | $583 | $129 | - | - | - |
$583
-
MMBtu
|
|
10 | 2.2136: Install / repair insulation on steam lines | $443 | $174 | - | - | - |
$443
-
MMBtu
|
|
11 | 2.2511: Insulate bare equipment | $273 | $147 | - | - | - |
$273
-
MMBtu
|
|
TOTAL RECOMMENDED | $12,201 | $15,670 |
$8,669
120,750
kWh
|
$2,601
-
kW-mo/yr
|
$(-102.0)
-
MMBtu
|
$1,033
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,576 | $13,144 |
$7,900
109,613
kWh
|
$2,601
-
kW-mo/yr
|
$(-102.0)
-
MMBtu
|
$177
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs