ITAC Assessment: ME0234
ITAC logo
ITAC Assessment: ME0234
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Hardwood Flooring
NAICS
n/a
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 550,000
ft2
Annual Production 5,350,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $246,691 3,456,038
kWh
Electricity Demand $79,588 8,020
kW-mo/yr
Electricity Fees $5,056 -
Natural Gas $6,882 755
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,936 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,899

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Water Consumption Savings Primary Product Savings By-product Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $38,400 $50,000 - - - - - - $38,400 - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $19,979 $12,932 $5,040
71,805
kWh
$1,431
-
kW-mo/yr
$(-2,136.0)
-
MMBtu
- - - $15,644 - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,153 $10,580 $6,364
90,856
kWh
$1,789
-
kW-mo/yr
- - - - - - - -
04 2.4133: Use most efficient type of electric motors $4,482 $4,476 $3,826
48,652
kWh
$656
-
kW-mo/yr
- - - - - - - -
05 2.4221: Install compressor air intakes in coolest locations $2,284 $800 $2,284
32,532
kWh
- - - - - - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $975 $500 $975
14,068
kWh
- - - - - - - - -
07 3.4115: Recover and reuse cooling water $12,512 $12,000 $(-3,675.0)
(-52,755)
kWh
$(-894.0)
-
kW-mo/yr
- $12,627
-
gal
- - - $4,454
-
Tgal
- -
08 3.6192: Use a less expensive method of waste removal $150 - - - - - - - - - - $150
09 3.6192: Use a less expensive method of waste removal $1,887 $3,000 - - - - - $1,887
-
lb
- - - -
10 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid $1,114 $7,000 $654
9,086
kWh
$357
-
kW-mo/yr
- - $9
-
gal
- - - $94 -
TOTAL RECOMMENDED $89,936 $101,288 $15,468
214,244
kWh
$3,339
-
kW-mo/yr
$(-2,136.0)
-
MMBtu
$12,627
-
gal
$9
-
gal
$1,887
-
lb
$54,044 $4,454
-
Tgal
$94 $150
TOTAL IMPLEMENTED $87,899 $98,288 $15,468
214,244
kWh
$3,339
-
kW-mo/yr
$(-2,136.0)
-
MMBtu
$12,627
-
gal
$9
-
gal
- $54,044 $4,454
-
Tgal
$94 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Water Consumption Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs