Assessment Year | 1999 |
---|---|
Principal Product | Hardwood Flooring |
NAICS |
n/a
|
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $10 M to 50M |
# of Employees | 190 |
Plant Area |
550,000
ft2
|
Annual Production | 5,350,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $246,691 | 3,456,038 |
kWh
|
$0.071 |
Electricity Demand | $79,588 | 8,020 |
kW-mo/yr
|
$9.92 |
Electricity Fees | $5,056 | - |
|
- |
Natural Gas | $6,882 | 755 |
MMBtu
|
$9.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,936 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $87,899 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Water Consumption Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $38,400 | $50,000 | - | - | - | - | - | - | $38,400 | - | - | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $19,979 | $12,932 |
$5,040
71,805
kWh
|
$1,431
-
kW-mo/yr
|
$(-2,136.0)
-
MMBtu
|
- | - | - | $15,644 | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,153 | $10,580 |
$6,364
90,856
kWh
|
$1,789
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $4,482 | $4,476 |
$3,826
48,652
kWh
|
$656
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $2,284 | $800 |
$2,284
32,532
kWh
|
- | - | - | - | - | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $975 | $500 |
$975
14,068
kWh
|
- | - | - | - | - | - | - | - | - | |
07 | 3.4115: Recover and reuse cooling water | $12,512 | $12,000 |
$(-3,675.0)
(-52,755)
kWh
|
$(-894.0)
-
kW-mo/yr
|
- |
$12,627
-
gal
|
- | - | - |
$4,454
-
Tgal
|
- | - | |
08 | 3.6192: Use a less expensive method of waste removal | $150 | - | - | - | - | - | - | - | - | - | - | $150 | |
09 | 3.6192: Use a less expensive method of waste removal | $1,887 | $3,000 | - | - | - | - | - |
$1,887
-
lb
|
- | - | - | - | |
10 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $1,114 | $7,000 |
$654
9,086
kWh
|
$357
-
kW-mo/yr
|
- | - |
$9
-
gal
|
- | - | - | $94 | - | |
TOTAL RECOMMENDED | $89,936 | $101,288 |
$15,468
214,244
kWh
|
$3,339
-
kW-mo/yr
|
$(-2,136.0)
-
MMBtu
|
$12,627
-
gal
|
$9
-
gal
|
$1,887
-
lb
|
$54,044 |
$4,454
-
Tgal
|
$94 | $150 | ||
TOTAL IMPLEMENTED | $87,899 | $98,288 |
$15,468
214,244
kWh
|
$3,339
-
kW-mo/yr
|
$(-2,136.0)
-
MMBtu
|
$12,627
-
gal
|
$9
-
gal
|
- | $54,044 |
$4,454
-
Tgal
|
$94 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Water Consumption Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs