ITAC Assessment: ME0231
ITAC logo
ITAC Assessment: ME0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product wood turnings
NAICS
n/a
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 55
Plant Area 15,400
ft2
Annual Production 800,000
thousand feet
Production Hrs. Annual 2,000
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,579 1,222,157
kWh
Electricity Demand $38,259 5,346
kW-mo/yr
Electricity Fees $407 -
Fuel Oil #2 $3,732 475
MMBtu
Wood $1,500 1,039
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,739 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,937

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,324 $1,486 $1,046
17,585
kWh
$4,278
-
kW-mo/yr
- - - -
02 2.4226: Use / purchase optimum sized compressor $1,365 $874 $1,365
22,860
kWh
- - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $914 $200 $914
15,240
kWh
- - - - -
04 2.8121: Apply for tax-free status for energy purchases $630 - - - - - $630 -
05 4.821: Pay bills on time to avoid late fees $408 - - - - - $408 -
06 2.4133: Use most efficient type of electric motors $309 $1,678 $265
4,396
kWh
$44
-
kW-mo/yr
- - - -
07 2.2515: Use optimum thickness insulation $350 $75 $350
5,862
kWh
- - - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $218 $680 $218
3,517
kWh
- - - - -
09 2.2136: Install / repair insulation on steam lines $332 $215 - - $332
-
MMBtu
- - -
10 3.2123: Convert to high volume low pressure (hvlp) paint guns $4,614 $740 - - - - - $4,614
11 3.3131: Use evaporation to concentrate material $2,275 $5,748 - - - $592
-
lb
- $1,683
TOTAL RECOMMENDED $16,739 $11,696 $4,158
69,460
kWh
$4,322
-
kW-mo/yr
$332
-
MMBtu
$592
-
lb
$1,038 $6,297
TOTAL IMPLEMENTED $13,937 $3,590 $3,675
61,547
kWh
$4,278
-
kW-mo/yr
$332
-
MMBtu
- $1,038 $4,614
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings Solid Waste (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs