Assessment Year | 1998 |
---|---|
Principal Product | wood turnings |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 55 |
Plant Area |
15,400
ft2
|
Annual Production | 800,000
thousand feet
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $78,579 | 1,222,157 |
kWh
|
$0.064 |
Electricity Demand | $38,259 | 5,346 |
kW-mo/yr
|
$7.16 |
Electricity Fees | $407 | - |
|
- |
Fuel Oil #2 | $3,732 | 475 |
MMBtu
|
$7.86 |
Wood | $1,500 | 1,039 |
MMBtu
|
$1.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,937 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,324 | $1,486 |
$1,046
17,585
kWh
|
$4,278
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4226: Use / purchase optimum sized compressor | $1,365 | $874 |
$1,365
22,860
kWh
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $914 | $200 |
$914
15,240
kWh
|
- | - | - | - | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $630 | - | - | - | - | - | $630 | - | |
05 | 4.821: Pay bills on time to avoid late fees | $408 | - | - | - | - | - | $408 | - | |
06 | 2.4133: Use most efficient type of electric motors | $309 | $1,678 |
$265
4,396
kWh
|
$44
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.2515: Use optimum thickness insulation | $350 | $75 |
$350
5,862
kWh
|
- | - | - | - | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $218 | $680 |
$218
3,517
kWh
|
- | - | - | - | - | |
09 | 2.2136: Install / repair insulation on steam lines | $332 | $215 | - | - |
$332
-
MMBtu
|
- | - | - | |
10 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $4,614 | $740 | - | - | - | - | - | $4,614 | |
11 | 3.3131: Use evaporation to concentrate material | $2,275 | $5,748 | - | - | - |
$592
-
lb
|
- | $1,683 | |
TOTAL RECOMMENDED | $16,739 | $11,696 |
$4,158
69,460
kWh
|
$4,322
-
kW-mo/yr
|
$332
-
MMBtu
|
$592
-
lb
|
$1,038 | $6,297 | ||
TOTAL IMPLEMENTED | $13,937 | $3,590 |
$3,675
61,547
kWh
|
$4,278
-
kW-mo/yr
|
$332
-
MMBtu
|
- | $1,038 | $4,614 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs