Assessment Year | 1997 |
---|---|
Principal Product | Machined Metal Products, Ball Valves |
NAICS |
n/a
|
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 75 |
Plant Area |
37,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,810
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $90,812 | 1,242,380 |
kWh
|
$0.073 |
Electricity Demand | $24,906 | 2,884 |
kW-mo/yr
|
$8.64 |
Electricity Fees | $1,441 | - |
|
- |
Natural Gas | $33,062 | 4,368 |
MMBtu
|
$7.57 |
LPG | $1,234 | 49 |
MMBtu
|
$25.18 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,629 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.131: Modify process to reduce material use/cost | $17,807 | $31,600 | n/a |
$(-1,260.0)
(-17,878)
kWh
|
$(-933.0)
-
kW-mo/yr
|
- | - | - | - | $20,000 | - |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,680 | $31,213 | n/a |
$5,151
73,564
kWh
|
$2,529
-
kW-mo/yr
|
- | - | - | - | - | - |
03 | 2.8121: Apply for tax-free status for energy purchases | $4,962 | - | n/a | - | - | - | - | - | $4,962 | - | - |
04 | 2.2437: Recover waste heat from equipment | $3,294 | $1,660 | n/a | - | - |
$3,294
-
MMBtu
|
- | - | - | - | - |
05 | 2.6218: Turn off equipment when not in use | $2,089 | - | n/a |
$2,089
29,894
kWh
|
- | - | - | - | - | - | - |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,820 | $725 | n/a |
$1,820
26,084
kWh
|
- | - | - | - | - | - | - |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,278 | $2,672 | n/a |
$319
4,689
kWh
|
$1,089
-
kW-mo/yr
|
- |
$(-130.0)
-
MMBtu
|
- | - | - | - |
08 | 2.2511: Insulate bare equipment | $410 | $264 | n/a |
$410
5,862
kWh
|
- | - | - | - | - | - | - |
09 | 2.8121: Apply for tax-free status for energy purchases | $395 | - | n/a | - | - | - | - | - | $395 | - | - |
10 | 4.821: Pay bills on time to avoid late fees | $306 | - | n/a | - | - | - | - | - | $306 | - | - |
11 | 2.8121: Apply for tax-free status for energy purchases | $205 | - | n/a | - | - | - | - | - | $205 | - | - |
12 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $4,383 | $12,000 | n/a | - | - | - | - |
$3,610
-
gal
|
- | - | $773 |
TOTAL RECOMMENDED | $44,629 | $80,134 |
$8,529
122,215
kWh
|
$2,685
-
kW-mo/yr
|
$3,294
-
MMBtu
|
$(-130.0)
-
MMBtu
|
$3,610
-
gal
|
$5,868 | $20,000 | $773 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs