| Assessment Year | 1997 |
|---|---|
| Principal Product | electric heaters |
| NAICS |
n/a
|
| SIC | 3634: Electric Housewares and Fans |
| Sales Range | $5 M to 10M |
| # of Employees | 135 |
| Plant Area |
57,000
ft2
|
| Annual Production | 20,000
units
|
| Production Hrs. Annual | 4,200
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,370 | 961,020 |
kWh
|
$0.069 |
| Electricity Demand | $20,696 | 3,024 |
kW-mo/yr
|
$6.84 |
| Electricity Fees | $5,497 | - |
|
- |
| LPG | $708 | 54 |
MMBtu
|
$13.11 |
| Fuel Oil #2 | $17,146 | 3,439 |
MMBtu
|
$4.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,076 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,157 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,045 | $25,615 |
$6,891
98,476
kWh
|
$2,154
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,936 | $4,075 |
$2,723
38,980
kWh
|
$2,071
-
kW-mo/yr
|
- |
$(-858.0)
-
MMBtu
|
- | - | - | - | |
| 03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,494 | $8,000 |
$3,029
43,376
kWh
|
$1,081
-
kW-mo/yr
|
$(-1,616.0)
-
MMBtu
|
- | - | - | - | - | |
| 04 | 4.623: Employ modular jigs to reduce process set-up time | $1,800 | $1,500 | - | - | - | - | - | $1,800 | - | - | |
| 05 | 2.8123: Pay utility bills on time | $1,361 | - | - | - | - | - | - | $1,361 | - | - | |
| 06 | 2.8114: Change rate schedules or other changes in utility service | $1,128 | $2,300 | - | - | - | - | - | $1,128 | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $642 | $325 |
$642
9,086
kWh
|
- | - | - | - | - | - | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $358 | $500 |
$358
4,982
kWh
|
- | - | - | - | - | - | - | |
| 09 | 2.8121: Apply for tax-free status for energy purchases | $120 | - | - | - | - | - | - | $120 | - | - | |
| 10 | 3.4151: Minimize water usage | $5,298 | $600 | - | - | - | - | - | - | - |
$5,298
-
Tgal
|
|
| 11 | 3.5311: Recover and reuse waste material | $4,029 | $12,577 | - | - | - | - |
$4,029
-
lb
|
- | - | - | |
| 12 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,079 | $6,200 | - | - | - | - |
$1,079
-
lb
|
- | - | - | |
| 13 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $786 | $525 | - | - | - | - | - | - | $786 | - | |
| TOTAL RECOMMENDED | $32,076 | $62,217 |
$13,643
194,900
kWh
|
$5,306
-
kW-mo/yr
|
$(-1,616.0)
-
MMBtu
|
$(-858.0)
-
MMBtu
|
$5,108
-
lb
|
$4,409 | $786 |
$5,298
-
Tgal
|
||
| TOTAL IMPLEMENTED | $23,157 | $47,842 |
$7,891
112,544
kWh
|
$2,154
-
kW-mo/yr
|
- | - |
$5,108
-
lb
|
$1,920 | $786 |
$5,298
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs