Assessment Year | 1996 |
---|---|
Principal Product | Toothpicks |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
86,016
ft2
|
Annual Production | 3,300,100
lb
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,780 | 237,691 |
kWh
|
$0.062 |
Electricity Demand | $23,564 | 2,465 |
kW-mo/yr
|
$9.56 |
Electricity Fees | $5,407 | - |
|
- |
Wood | $124,800 | 44,928 |
MMBtu
|
$2.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,839 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,638 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $24,412 | $4,200 |
$24,412
348,769
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,122 | $8,122 |
$6,998
101,114
kWh
|
$1,124
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,460 | $3,253 |
$3,460
49,531
kWh
|
- | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $2,150 | $2,150 | - | - |
$2,150
-
MMBtu
|
- | - | |
05 | 4.444: Install system to collect scrap | $1,800 | $1,800 | - | - | - | - | $1,800 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,044 | $1,044 |
$1,044
14,947
kWh
|
- | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,206 | $1,034 |
$1,206
17,292
kWh
|
- | - | - | - | |
08 | 2.2511: Insulate bare equipment | $8,789 | $500 | - | - |
$8,784
-
MMBtu
|
$5
-
lb
|
- | |
09 | 2.2136: Install / repair insulation on steam lines | $856 | $646 | - | - |
$855
-
MMBtu
|
$1
-
lb
|
- | |
TOTAL RECOMMENDED | $51,839 | $22,749 |
$37,120
531,653
kWh
|
$1,124
-
kW-mo/yr
|
$11,789
-
MMBtu
|
$6
-
lb
|
$1,800 | ||
TOTAL IMPLEMENTED | $18,638 | $18,049 |
$12,708
182,884
kWh
|
$1,124
-
kW-mo/yr
|
$3,005
-
MMBtu
|
$1
-
lb
|
$1,800 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs