ITAC Assessment: LE0151
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Chewing Gum Base
NAICS 311340: Nonchocolate Confectionery Manufacturing
SIC 2067: Chewing Gum
Sales Range $50
M
to 100
M
# of Employees 202
Plant Area 550,000
ft2
Annual Production 80,000,000
lb
Production Hrs. Annual 6,912
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $662,604 9,903,275
kWh
Electricity Demand $171,644 21,982
kW-mo/yr
Natural Gas $734,138 117,435
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,577 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $62,558

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.4323: Use optimum size and capacity equipment $3,947 $3,000 $3,947
59,003
kWh
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $13,069 - $10,431
155,928
kWh
$2,638
-
kW-mo/yr
- - -
03 2.2515: Use optimum thickness insulation $51,426 $6,735 - - - $51,426
-
MMBtu
-
04 2.4314: Use synthetic lubricant $7,733 $1,000 $6,170
92,234
kWh
$1,563
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $1,064 $4,425 $1,064
15,904
kWh
- - - -
06 2.3132: Recharge batteries on during off-peak demand periods $1,947 - - - $1,947 - -
07 2.3134: Shift from daytime to nighttime operation $4,270 - - - - - $4,270
08 2.1233: Analyze flue gas for proper air/fuel ratio $6,121 $1,000 - - - $6,121
-
MMBtu
-
TOTAL RECOMMENDED $89,577 $16,160 $21,612
323,069
kWh
$4,201
-
kW-mo/yr
$1,947 $57,547
-
MMBtu
$4,270
TOTAL IMPLEMENTED $62,558 $15,160 $5,011
74,907
kWh
- - $57,547
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs