Assessment Year | 1996 |
---|---|
Principal Product | newspapers |
NAICS |
n/a
|
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $10 M to 50M |
# of Employees | 274 |
Plant Area |
44,000
ft2
|
Annual Production | 8,221,454
lb
|
Production Hrs. Annual | 7,300
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $109,131 | 1,512,016 |
kWh
|
$0.072 |
Electricity Demand | $33,136 | 3,758 |
kW-mo/yr
|
$8.82 |
Electricity Fees | $1,865 | - |
|
- |
Fuel Oil #2 | $909 | 195 |
MMBtu
|
$4.66 |
Fuel Oil #6 | $18,274 | 8,816 |
MMBtu
|
$2.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,610 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,571 | $18,242 |
$4,597
65,358
kWh
|
$974
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,836 | $600 |
$2,836
40,445
kWh
|
- | - | - | |
03 | 2.2135: Repair and eliminate steam leaks | $2,160 | $100 | - | - |
$2,160
-
MMBtu
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,921 | - |
$1,921
27,550
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,018 | $1,050 |
$1,018
14,654
kWh
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $675 | $930 | - | - |
$675
-
MMBtu
|
- | |
07 | 3.5313: Increase amount of waste recovered for resale | $675 | - | - | - | - |
$675
-
lb
|
|
TOTAL RECOMMENDED | $14,856 | $20,922 |
$10,372
148,007
kWh
|
$974
-
kW-mo/yr
|
$2,835
-
MMBtu
|
$675
-
lb
|
||
TOTAL IMPLEMENTED | $8,610 | $2,680 |
$5,775
82,649
kWh
|
- |
$2,835
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs