| Assessment Year | 1996 |
|---|---|
| Principal Product | plastic cutlery |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
45,900
ft2
|
| Annual Production | 17,120,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $561,141 | 11,361,079 |
kWh
|
$0.049 |
| Electricity Demand | $134,744 | 21,744 |
kW-mo/yr
|
$6.20 |
| Electricity Fees | $9,935 | - |
|
- |
| LPG | $10,861 | 1,368 |
MMBtu
|
$7.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,423 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,168 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $5,103 | $9,087 | - | - | - | $5,103 | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,255 | $6,000 |
$2,255
45,135
kWh
|
- | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $2,902 | $400 |
$2,902
57,737
kWh
|
- | - | - | |
| 04 | 2.8121: Apply for tax-free status for energy purchases | $1,748 | - | - | - | - | $1,748 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,615 | $4,430 |
$1,380
27,550
kWh
|
$235
-
kW-mo/yr
|
- | - | |
| 06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $2,800 | - | - | - |
$2,800
-
lb
|
- | |
| TOTAL RECOMMENDED | $16,423 | $19,917 |
$6,537
130,422
kWh
|
$235
-
kW-mo/yr
|
$2,800
-
lb
|
$6,851 | ||
| TOTAL IMPLEMENTED | $14,168 | $13,917 |
$4,282
85,287
kWh
|
$235
-
kW-mo/yr
|
$2,800
-
lb
|
$6,851 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs