| Assessment Year | 2001 |
|---|---|
| Principal Product | Machine tools |
| NAICS |
n/a
|
| SIC | 3542: Machine Tools, Metal Forming Types |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
95,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $183,561 | 1,852,120 |
kWh
|
$0.099 |
| Electricity Fees | $3,186 | - |
|
- |
| Natural Gas | $47,305 | 9,561 |
MMBtu
|
$4.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $57,423 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,050 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,160 | $12,637 |
$3,160
31,351
kWh
|
- | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $29,810 | $40,000 | - | $29,810 | - | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $9,050 | $3,150 | - | - |
$9,050
-
MMBtu
|
|
| 04 | 4.512: Condense operation into one building | $12,695 | $10,000 |
$9,435
95,200
kWh
|
- |
$3,260
-
MMBtu
|
|
| 05 | 2.7492: Use proper thickness of insulation on building envelope | $2,708 | $1,250 | - | - |
$2,708
-
MMBtu
|
|
| TOTAL RECOMMENDED | $57,423 | $67,037 |
$12,595
126,551
kWh
|
$29,810 |
$15,018
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,050 | $3,150 | - | - |
$9,050
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs