ITAC Assessment: UM0191
ITAC logo
ITAC Assessment: UM0191
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Machine tools
NAICS
n/a
SIC 3542: Machine Tools, Metal Forming Types
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 95,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,210
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $183,561 1,852,120
kWh
Electricity Fees $3,186 -
Natural Gas $47,305 9,561
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,423 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,050

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,160 $12,637 $3,160
31,351
kWh
- -
02 2.8114: Change rate schedules or other changes in utility service $29,810 $40,000 - $29,810 -
03 2.7243: Improve air circulation with destratification fans / other methods $9,050 $3,150 - - $9,050
-
MMBtu
04 4.512: Condense operation into one building $12,695 $10,000 $9,435
95,200
kWh
- $3,260
-
MMBtu
05 2.7492: Use proper thickness of insulation on building envelope $2,708 $1,250 - - $2,708
-
MMBtu
TOTAL RECOMMENDED $57,423 $67,037 $12,595
126,551
kWh
$29,810 $15,018
-
MMBtu
TOTAL IMPLEMENTED $9,050 $3,150 - - $9,050
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs