Assessment Year | 1996 |
---|---|
Principal Product | shoes |
NAICS |
n/a
|
SIC | 3149: Footwear, Except Rubber, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
80,000
ft2
|
Annual Production | 215,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,832 | 1,197,831 |
kWh
|
$0.070 |
Electricity Demand | $45,053 | 5,422 |
kW-mo/yr
|
$8.31 |
Electricity Fees | $2,119 | - |
|
- |
Natural Gas | $117 | 4 |
MMBtu
|
$29.25 |
Fuel Oil #6 | $26,465 | 8,002 |
MMBtu
|
$3.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,791 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,195 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,271 | $27,695 |
$5,631
80,305
kWh
|
$3,640
-
kW-mo/yr
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,099 | $632 |
$2,809
50,410
kWh
|
- |
$(-710.0)
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $1,990 | $1,130 |
$1,990
28,429
kWh
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,653 | $750 |
$1,653
23,740
kWh
|
- | - | - | |
05 | 2.2153: Close off unneeded steam lines | $2,370 | $200 | - | - |
$2,370
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,212 | $1,000 |
$1,212
17,292
kWh
|
- | - | - | |
07 | 2.6218: Turn off equipment when not in use | $1,069 | - |
$1,069
15,240
kWh
|
- | - | - | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $923 | $400 | - | - |
$923
-
MMBtu
|
- | |
09 | 2.2511: Insulate bare equipment | $596 | $305 |
$596
8,499
kWh
|
- | - | - | |
10 | 2.8123: Pay utility bills on time | $1,608 | - | - | - | - | $1,608 | |
TOTAL RECOMMENDED | $22,791 | $32,112 |
$14,960
223,915
kWh
|
$3,640
-
kW-mo/yr
|
$2,583
-
MMBtu
|
$1,608 | ||
TOTAL IMPLEMENTED | $22,195 | $31,807 |
$14,364
215,416
kWh
|
$3,640
-
kW-mo/yr
|
$2,583
-
MMBtu
|
$1,608 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs