Assessment Year | 2003 |
---|---|
Principal Product | Aliminum Extrusion |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
65,000
ft2
|
Annual Production | 18,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $275,826 | 2,495,489 |
kWh
|
$0.11 |
Electricity Demand | $82,673 | 6,972 |
kW-mo/yr
|
$11.86 |
Natural Gas | $58,652 | 13,610 |
MMBtu
|
$4.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $111,103 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,860 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $58,217 | $20,000 |
$44,554
403,200
kWh
|
$13,663
-
kW-mo/yr
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,529 | $11,275 |
$15,256
138,062
kWh
|
$3,273
-
kW-mo/yr
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,447 | $14,000 |
$7,777
70,384
kWh
|
$1,670
-
kW-mo/yr
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $7,406 | - |
$6,097
55,200
kWh
|
$1,309
-
kW-mo/yr
|
- | - | |
05 | 4.652: Replace existing equipment with more suitable substitutes | $5,962 | $1,350 |
$934
8,452
kWh
|
$5,028
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,860 | $160 |
$4,001
36,210
kWh
|
$859
-
kW-mo/yr
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $3,882 | $15,000 | - | - |
$3,882
-
MMBtu
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,800 | $5,000 | - | - | - | $2,800 | |
TOTAL RECOMMENDED | $111,103 | $66,785 |
$78,619
711,508
kWh
|
$25,802
-
kW-mo/yr
|
$3,882
-
MMBtu
|
$2,800 | ||
TOTAL IMPLEMENTED | $4,860 | $160 |
$4,001
36,210
kWh
|
$859
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs