Assessment Year | 1996 |
---|---|
Principal Product | Shoes |
NAICS |
n/a
|
SIC | 3143: Men's Footwear, Except Athletic |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
32,983
ft2
|
Annual Production | 472,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,298 | 936,987 |
kWh
|
$0.071 |
Electricity Demand | $40,070 | 4,851 |
kW-mo/yr
|
$8.26 |
Electricity Fees | $1,108 | - |
|
- |
Fuel Oil #2 | $4,478 | 947 |
MMBtu
|
$4.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,162 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,162 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,275 | $44,351 |
$12,791
115,475
kWh
|
$7,484
-
kW-mo/yr
|
- | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,098 | $4,000 |
$3,771
53,927
kWh
|
$2,450
-
kW-mo/yr
|
$(-1,123.0)
-
MMBtu
|
|
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,576 | $1,839 |
$2,521
35,756
kWh
|
$2,041
-
kW-mo/yr
|
$(-986.0)
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $1,619 | $2,930 |
$1,619
22,860
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $1,224 | $928 |
$1,224
17,585
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $370 | $400 |
$370
5,275
kWh
|
- | - | |
TOTAL RECOMMENDED | $32,162 | $54,448 |
$22,296
250,878
kWh
|
$11,975
-
kW-mo/yr
|
$(-2,109.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $32,162 | $54,448 |
$22,296
250,878
kWh
|
$11,975
-
kW-mo/yr
|
$(-2,109.0)
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs