ITAC Assessment: ME0178
ITAC logo
ITAC Assessment: ME0178
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Shoes
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 32,983
ft2
Annual Production 472,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,298 936,987
kWh
Electricity Demand $40,070 4,851
kW-mo/yr
Electricity Fees $1,108 -
Fuel Oil #2 $4,478 947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,162 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,162

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $20,275 $44,351 $12,791
115,475
kWh
$7,484
-
kW-mo/yr
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,098 $4,000 $3,771
53,927
kWh
$2,450
-
kW-mo/yr
$(-1,123.0)
-
MMBtu
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,576 $1,839 $2,521
35,756
kWh
$2,041
-
kW-mo/yr
$(-986.0)
-
MMBtu
04 2.2511: Insulate bare equipment $1,619 $2,930 $1,619
22,860
kWh
- -
05 2.2437: Recover waste heat from equipment $1,224 $928 $1,224
17,585
kWh
- -
06 2.4221: Install compressor air intakes in coolest locations $370 $400 $370
5,275
kWh
- -
TOTAL RECOMMENDED $32,162 $54,448 $22,296
250,878
kWh
$11,975
-
kW-mo/yr
$(-2,109.0)
-
MMBtu
TOTAL IMPLEMENTED $32,162 $54,448 $22,296
250,878
kWh
$11,975
-
kW-mo/yr
$(-2,109.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs