ITAC Assessment: ME0177
ITAC logo
ITAC Assessment: ME0177
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Shoes
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 155
Plant Area 31,250
ft2
Annual Production 328,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,823 655,041
kWh
Electricity Demand $26,951 2,148
kW-mo/yr
Electricity Fees $2,281 -
Fuel Oil #2 $7,943 1,751
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,754 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,974

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,845 $10,000 $2,620
37,222
kWh
$4,579
-
kW-mo/yr
$(-1,354.0)
-
MMBtu
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,749 $5,000 $1,575
22,274
kWh
$636
-
kW-mo/yr
- $(-462.0)
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $1,186 $600 - - - $1,186
-
MMBtu
04 2.2511: Insulate bare equipment $835 $371 $835
12,016
kWh
- - -
05 2.4221: Install compressor air intakes in coolest locations $754 $300 $754
8,499
kWh
- - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $385 $750 $385
5,569
kWh
- - -
TOTAL RECOMMENDED $10,754 $17,021 $6,169
85,580
kWh
$5,215
-
kW-mo/yr
$(-1,354.0)
-
MMBtu
$724
-
MMBtu
TOTAL IMPLEMENTED $1,974 $1,421 $1,974
26,084
kWh
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs