ITAC Assessment: ME0174
ITAC logo
ITAC Assessment: ME0174
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Carbonated Beverages
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 161,000
ft2
Annual Production 3,400,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,215 1,754,396
kWh
Fuel Oil #4 $40,319 13,237
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,492 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,879

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings
01 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $2,666 $8,090 $2,666
19,637
kWh
- - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,372 $5,406 $2,623
38,394
kWh
$(-251.0)
-
MMBtu
- - -
03 2.4221: Install compressor air intakes in coolest locations $993 $200 $993
28,429
kWh
- - - -
04 2.8121: Apply for tax-free status for energy purchases $785 - - - - - $785
05 2.1213: Direct warmest air to combustion intake $196 $400 - $196
-
MMBtu
- - -
06 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $439 $1,135 $439
6,155
kWh
- - - -
07 2.6218: Turn off equipment when not in use $410 - $410
4,689
kWh
- - - -
08 2.8118: Check for accuracy of utility / power meters $15,905 - - - - - $15,905
09 3.4114: Replace city water with recycled water via cooling tower $6,875 $30,000 - - $6,875
-
Tgal
- -
10 3.5142: Treat and reuse equipment cleaning solutions $1,851 $233 - - $39
-
Tgal
$1,812
-
gal
-
TOTAL RECOMMENDED $32,492 $45,464 $7,131
97,304
kWh
$(-55.0)
-
MMBtu
$6,914
-
Tgal
$1,812
-
gal
$16,690
TOTAL IMPLEMENTED $17,879 $600 $993
28,429
kWh
$196
-
MMBtu
- - $16,690
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #4 Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs