| Assessment Year | 1995 |
|---|---|
| Principal Product | insulation board |
| NAICS |
n/a
|
| SIC | 3086: Plastics Foam Products |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
87,000
ft2
|
| Annual Production | 69,732,000
thousand feet
|
| Production Hrs. Annual | 5,760
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,855 | 1,936,694 |
kWh
|
$0.097 |
| LPG | $19,895 | 2,800 |
MMBtu
|
$7.11 |
| Fuel Oil #2 | $7,883 | 1,685 |
MMBtu
|
$4.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,611 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $42,641 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $23,325 | $55,000 |
$18,128
201,348
kWh
|
$5,197
-
MMBtu
|
- | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $15,977 | $6,730 |
$14,250
146,835
kWh
|
- |
$1,727
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,002 | $8,064 |
$11,002
146,249
kWh
|
- | - | - | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,232 | $8,000 |
$4,695
102,579
kWh
|
$(-463.0)
-
MMBtu
|
- | - | - | |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $2,200 | - | - |
$2,200
-
MMBtu
|
- | - | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,736 | $5,000 |
$1,903
46,893
kWh
|
$(-167.0)
-
MMBtu
|
- | - | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $290 | $200 |
$290
4,103
kWh
|
- | - | - | - | |
| 08 | 3.4151: Minimize water usage | $849 | $110 | - | - | - |
$325
-
Tgal
|
$524
-
Tgal
|
|
| TOTAL RECOMMENDED | $59,611 | $83,104 |
$50,268
648,007
kWh
|
$6,767
-
MMBtu
|
$1,727
-
MMBtu
|
$325
-
Tgal
|
$524
-
Tgal
|
||
| TOTAL IMPLEMENTED | $42,641 | $62,040 |
$32,668
352,286
kWh
|
$7,397
-
MMBtu
|
$1,727
-
MMBtu
|
$325
-
Tgal
|
$524
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs