Assessment Year | 1995 |
---|---|
Principal Product | Firearms, human restraints |
NAICS |
n/a
|
SIC | 3462: Iron and Steel Forgings |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
36,000
ft2
|
Annual Production | 290,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $125,237 | 1,616,940 |
kWh
|
$0.077 |
Fuel Oil #2 | $4,011 | 746 |
MMBtu
|
$5.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $24,684 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,119 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,304 | $43,147 |
$15,304
216,589
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,696 | $600 |
$4,696
76,202
kWh
|
- | - | - | |
03 | 2.2511: Insulate bare equipment | $789 | $600 |
$789
11,430
kWh
|
- | - | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $645 | - | - | - | $645 | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $474 | $200 |
$474
6,741
kWh
|
- | - | - | |
06 | 2.7135: Install occupancy sensors | $509 | $1,800 |
$509
7,034
kWh
|
- | - | - | |
07 | 3.4115: Recover and reuse cooling water | $1,239 | $2,650 | - |
$851
-
Tgal
|
- |
$388
-
Tgal
|
|
08 | 3.4151: Minimize water usage | $1,028 | $570 | - |
$560
-
Tgal
|
- |
$468
-
Tgal
|
|
TOTAL RECOMMENDED | $24,684 | $49,567 |
$21,772
317,996
kWh
|
$1,411
-
Tgal
|
$645 |
$856
-
Tgal
|
||
TOTAL IMPLEMENTED | $21,119 | $43,947 |
$20,474
299,532
kWh
|
- | $645 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs