| Assessment Year | 1995 |
|---|---|
| Principal Product | PRINTED CALENDARS |
| NAICS |
n/a
|
| SIC | 2759: Commercial Printing, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 400 |
| Plant Area |
180,000
ft2
|
| Annual Production | 60,000,000
pieces
|
| Production Hrs. Annual | 5,250
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $235,659 | 2,372,216 |
kWh
|
$0.099 |
| Fuel Oil #2 | $12,915 | 3,080 |
MMBtu
|
$4.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,521 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,441 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,120 | $16,036 |
$7,120
71,219
kWh
|
- | - | - | - | |
| 02 | 2.2515: Use optimum thickness insulation | $2,340 | $870 |
$2,340
23,447
kWh
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,447 | $300 |
$1,447
14,654
kWh
|
- | - | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,288 | $800 |
$1,288
12,896
kWh
|
- | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $1,175 | $3,519 | - |
$1,175
-
MMBtu
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $1,050 | $315 | - |
$1,050
-
MMBtu
|
- | - | - | |
| 07 | 2.8121: Apply for tax-free status for energy purchases | $736 | - | - | - | - | - | $736 | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $455 | $400 | - |
$455
-
MMBtu
|
- | - | - | |
| 09 | 3.5316: Contract a wood pallet recycling company | $455 | - | - | - | - |
$455
-
lb
|
- | |
| 10 | 3.5121: Recycle waste ink and cleanup solvent | $455 | $260 | - | - |
$455
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $16,521 | $22,500 |
$12,195
122,216
kWh
|
$2,680
-
MMBtu
|
$455
-
gal
|
$455
-
lb
|
$736 | ||
| TOTAL IMPLEMENTED | $7,441 | $5,889 |
$5,075
50,997
kWh
|
$1,630
-
MMBtu
|
- | - | $736 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs