ITAC Assessment: ME0148
ITAC logo
ITAC Assessment: ME0148
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Boots
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 195
Plant Area 115,000
ft2
Annual Production 3,450,000
pieces
Production Hrs. Annual 3,840
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $106,103 1,033,118
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,402 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,681

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $728 $200 $728
7,034
kWh
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $484 $500 $484
4,689
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $469 $380 $469
4,689
kWh
-
04 2.7135: Install occupancy sensors $455 $300 $455
4,396
kWh
-
05 2.8123: Pay utility bills on time $266 - - $266
TOTAL RECOMMENDED $2,402 $1,380 $2,136
20,808
kWh
$266
TOTAL IMPLEMENTED $1,681 $1,080 $1,681
16,412
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs