Assessment Year | 1993 |
---|---|
Principal Product | Woolen Cloth |
NAICS |
n/a
|
SIC | 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing) |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
100,000
ft2
|
Annual Production | 6,667
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $239,091 | 2,629,543 |
kWh
|
$0.091 |
LPG | $3,355 | 433 |
MMBtu
|
$7.75 |
Fuel Oil #6 | $133,944 | 54,500 |
MMBtu
|
$2.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $141,113 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,565 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings |
---|---|---|---|---|---|---|---|
01 | 2.1213: Direct warmest air to combustion intake | $1,628 | $800 | - |
$1,628
-
MMBtu
|
- | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $106,916 | $100,000 |
$214,620
2,360,199
kWh
|
$(-120,245.0)
-
MMBtu
|
$12,541
-
MMBtu
|
|
03 | 2.3212: Optimize plant power factor | $1,882 | $2,500 |
$1,882
-
kWh
|
- | - | |
04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $1,080 | $3,000 | - |
$1,080
-
MMBtu
|
- | |
05 | 2.4221: Install compressor air intakes in coolest locations | $965 | $100 |
$965
10,551
kWh
|
- | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $25,600 | $2,000 |
$25,600
281,946
kWh
|
- | - | |
07 | 2.8123: Pay utility bills on time | $3,042 | - |
$3,042
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $141,113 | $108,400 |
$246,109
2,652,696
kWh
|
$(-117,537.0)
-
MMBtu
|
$12,541
-
MMBtu
|
||
TOTAL IMPLEMENTED | $26,565 | $2,100 |
$26,565
292,497
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs