ITAC Assessment: ME0114
ITAC logo
ITAC Assessment: ME0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Footwear
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $5
M
to 10
M
# of Employees 170
Plant Area 100,000
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 1,960
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $138,795 1,271,395
kWh
Fuel Oil #2 $1,308 215
MMBtu
Fuel Oil #6 $5,080 1,739
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,855 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $990 $500 $990
7,620
kWh
-
02 2.2437: Recover waste heat from equipment $550 $250 $550
4,982
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $215 $100 $215
2,052
kWh
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,503 $4,500 $3,825
51,876
kWh
$(-1,322.0)
-
MMBtu
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $597 $1,250 $770
7,034
kWh
$(-173.0)
-
MMBtu
TOTAL RECOMMENDED $4,855 $6,600 $6,350
73,564
kWh
$(-1,495.0)
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs