ITAC Assessment: ME0108
ITAC logo
ITAC Assessment: ME0108
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Side & Split Leather
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 340,000
ft2
Annual Production 3,800,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,159,705 13,227,433
kWh
Fuel Oil #2 $14,207 3,136
MMBtu
Fuel Oil #6 $350,143 158,728
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,502 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,512

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings
01 2.8123: Pay utility bills on time $5,548 - $5,548
-
kWh
-
02 2.3212: Optimize plant power factor $5,990 $5,000 $5,990
-
kWh
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $9,170 $250 - $9,170
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,804 $18,100 $11,804
135,991
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $1,990 $500 $1,990
22,860
kWh
-
TOTAL RECOMMENDED $34,502 $23,850 $25,332
158,851
kWh
$9,170
-
MMBtu
TOTAL IMPLEMENTED $28,512 $18,850 $19,342
158,851
kWh
$9,170
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs