ITAC Assessment: MAS033
ITAC logo
ITAC Assessment: MAS033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Flock Fiber
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2261: Finishers of Broadwoven Fabrics of Cotton
Sales Range $5
M
to 10
M
# of Employees 25
Plant Area 95,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 3,000
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $174,906 1,764,600
kWh
Electricity Demand $31,705 8,088
kW-mo/yr
Electricity Fees $2,400 -
Natural Gas $220,194 20,703
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,791 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,549

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,549 $7,500 $8,549
86,268
kWh
-
02 2.2414: Use waste heat from hot flue gases to preheat $7,256 $34,000 - $7,256
-
MMBtu
03 2.2511: Insulate bare equipment $1,224 $730 - $1,224
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $762 $3,450 $762
7,692
kWh
-
TOTAL RECOMMENDED $17,791 $45,680 $9,311
93,960
kWh
$8,480
-
MMBtu
TOTAL IMPLEMENTED $8,549 $7,500 $8,549
86,268
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs