ITAC Assessment: MA0729
ITAC logo
ITAC Assessment: MA0729
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product printed fabric
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2261: Finishers of Broadwoven Fabrics of Cotton
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 246,300
ft2
Annual Production 30,000
thousand feet
Production Hrs. Annual 4,400
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $467,238 3,853,400
kWh
Electricity Demand $174,041 16,569
kW-mo/yr
Electricity Fees $42,650 -
Natural Gas $900,649 98,936
MMBtu
Fuel Oil #6 $11,663 669
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,073 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,619

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
01 2.1243: Use heat from boiler blowdown to preheat boiler feed water $25,718 $11,750 - $8,172
-
MMBtu
$17,546
-
gal
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $14,490 $500 $14,490
119,460
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,956 $3,300 $8,956
73,836
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,114 $9,050 $8,114
66,896
kWh
- -
05 2.2136: Install / repair insulation on steam lines $2,622 $2,690 - $2,622
-
MMBtu
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,173 $200 $1,173
9,672
kWh
- -
TOTAL RECOMMENDED $61,073 $27,490 $32,733
269,864
kWh
$10,794
-
MMBtu
$17,546
-
gal
TOTAL IMPLEMENTED $24,619 $4,000 $24,619
202,968
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs