ITAC Assessment: MA0713
ITAC logo
ITAC Assessment: MA0713
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product repaired helicopter pats
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 125,800
ft2
Annual Production 1,000
ton
Production Hrs. Annual 4,768
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $382,677 3,573,600
kWh
Electricity Demand $137,408 8,375
kW-mo/yr
Electricity Fees $7,539 -
Natural Gas $182,412 15,631
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,589 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,582

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.2691: Shut off cooling if cold outside air will cool process $7,896 $22,000 $7,896
74,497
kWh
- -
02 2.7314: Reduce ventilation air $7,745 $500 $4,295
40,523
kWh
$3,450
-
MMBtu
-
03 2.4226: Use / purchase optimum sized compressor $7,547 $44,500 $(-8,453.0)
(-79,816)
kWh
- $16,000
04 2.7243: Improve air circulation with destratification fans / other methods $3,564 $16,800 $(-818.0)
(-7,715)
kWh
$4,382
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,837 $1,720 $3,837
36,205
kWh
- -
TOTAL RECOMMENDED $30,589 $85,520 $6,757
63,694
kWh
$7,832
-
MMBtu
$16,000
TOTAL IMPLEMENTED $11,582 $2,220 $8,132
76,728
kWh
$3,450
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs