Assessment Year | 2012 |
---|---|
Principal Product | Newspaper printing |
NAICS | 511110: Newspaper Publishers |
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $50 M to 100M |
# of Employees | 158 |
Plant Area |
145,000
ft2
|
Annual Production | 25,000
ton
|
Production Hrs. Annual | 3,650
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $492,823 | 5,716,800 |
kWh
|
$0.086 |
Electricity Demand | $186,900 | 28,665 |
kW-mo/yr
|
$6.52 |
Electricity Fees | $1,755 | - |
|
- |
Natural Gas | $37,555 | 3,845 |
MMBtu
|
$9.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $68,944 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,694 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,785 | $80,000 |
$22,571
261,809
kWh
|
- |
$7,214
-
MMBtu
|
|
02 | 2.3212: Optimize plant power factor | $12,823 | $24,111 | - |
$12,823
-
kW-mo/yr
|
- | |
03 | 2.7314: Reduce ventilation air | $3,642 | $6,000 |
$894
10,368
kWh
|
- |
$2,748
-
MMBtu
|
|
04 | 2.7135: Install occupancy sensors | $9,553 | $47,000 |
$9,553
110,807
kWh
|
- | - | |
05 | 2.7135: Install occupancy sensors | $7,855 | $11,200 |
$7,855
91,109
kWh
|
- | - | |
06 | 2.7442: Keep doors and windows shut when not on use | $5,286 | $500 |
$1,326
15,377
kWh
|
- |
$3,960
-
MMBtu
|
|
TOTAL RECOMMENDED | $68,944 | $168,811 |
$42,199
489,470
kWh
|
$12,823
-
kW-mo/yr
|
$13,922
-
MMBtu
|
||
TOTAL IMPLEMENTED | $22,694 | $58,700 |
$18,734
217,293
kWh
|
- |
$3,960
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs