Assessment Year | 2011 |
---|---|
Principal Product | clothes |
NAICS | 314999: All Other Miscellaneous Textile Product Mills |
SIC | 2299: Textile goods, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 102 |
Plant Area |
6,000
ft2
|
Annual Production | 624,000
pieces
|
Production Hrs. Annual | 3,744
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,672 | 675,280 |
kWh
|
$0.099 |
Electricity Demand | $46,558 | 2,082 |
kW-mo/yr
|
$22.36 |
Electricity Fees | $7,816 | - |
|
- |
Natural Gas | $222,932 | 17,011 |
MMBtu
|
$13.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,039 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,520 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $36,635 | $200,000 |
$55,881
564,452
kWh
|
$20,125
-
kW-mo/yr
|
$(-29,864.0)
-
MMBtu
|
$(-9,507.0) | |
02 | 2.2136: Install / repair insulation on steam lines | $4,780 | $3,550 | - | - |
$4,780
-
MMBtu
|
- | |
03 | 2.2691: Shut off cooling if cold outside air will cool process | $1,556 | $15,000 |
$1,556
15,727
kWh
|
- | - | - | |
04 | 2.7135: Install occupancy sensors | $1,328 | $2,220 |
$1,328
13,418
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $740 | $200 |
$740
7,465
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $45,039 | $220,970 |
$59,505
601,062
kWh
|
$20,125
-
kW-mo/yr
|
$(-25,084.0)
-
MMBtu
|
$(-9,507.0) | ||
TOTAL IMPLEMENTED | $5,520 | $3,750 |
$740
7,465
kWh
|
- |
$4,780
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs