ITAC Assessment: MA0671
ITAC logo
ITAC Assessment: MA0671
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product clothes
NAICS 314999: All Other Miscellaneous Textile Product Mills
SIC 2299: Textile goods, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 102
Plant Area 6,000
ft2
Annual Production 624,000
pieces
Production Hrs. Annual 3,744
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,672 675,280
kWh
Electricity Demand $46,558 2,082
kW-mo/yr
Electricity Fees $7,816 -
Natural Gas $222,932 17,011
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,039 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $36,635 $200,000 $55,881
564,452
kWh
$20,125
-
kW-mo/yr
$(-29,864.0)
-
MMBtu
$(-9,507.0)
02 2.2136: Install / repair insulation on steam lines $4,780 $3,550 - - $4,780
-
MMBtu
-
03 2.2691: Shut off cooling if cold outside air will cool process $1,556 $15,000 $1,556
15,727
kWh
- - -
04 2.7135: Install occupancy sensors $1,328 $2,220 $1,328
13,418
kWh
- - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $740 $200 $740
7,465
kWh
- - -
TOTAL RECOMMENDED $45,039 $220,970 $59,505
601,062
kWh
$20,125
-
kW-mo/yr
$(-25,084.0)
-
MMBtu
$(-9,507.0)
TOTAL IMPLEMENTED $5,520 $3,750 $740
7,465
kWh
- $4,780
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs