ITAC Assessment: MA0669
ITAC logo
ITAC Assessment: MA0669
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Processed fish and scallops
NAICS 311710: Seafood Product Preparation and Packaging
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $100
M
to 500
M
# of Employees 238
Plant Area 130,000
ft2
Annual Production 49,000,000
lb
Production Hrs. Annual 5,880
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,460,023 9,465,120
kWh
Electricity Demand $249,063 26,825
kW-mo/yr
Electricity Fees $10,800 -
Natural Gas $306,945 27,736
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,962 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,211

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1224: Replace boiler $28,774 $63,300 - - $28,774
-
MMBtu
02 2.2511: Insulate bare equipment $12,439 $25,000 - - $12,439
-
MMBtu
03 2.3212: Optimize plant power factor $10,179 $11,190 - $10,179
-
kW-mo/yr
-
04 2.6218: Turn off equipment when not in use $7,848 $1,500 $7,848
50,960
kWh
- -
05 2.4226: Use / purchase optimum sized compressor $3,576 $25,250 $3,576
23,220
kWh
- -
06 2.2511: Insulate bare equipment $736 $349 - - $736
-
MMBtu
07 2.2511: Insulate bare equipment $410 $550 - - $410
-
MMBtu
TOTAL RECOMMENDED $63,962 $127,139 $11,424
74,180
kWh
$10,179
-
kW-mo/yr
$42,359
-
MMBtu
TOTAL IMPLEMENTED $47,211 $76,540 $7,848
50,960
kWh
$10,179
-
kW-mo/yr
$29,184
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs