| Assessment Year | 1999 |
|---|---|
| Principal Product | Concrete Products |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
36,000
ft2
|
| Annual Production | 50,000
ton
|
| Production Hrs. Annual | 2,210
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $69,968 | 1,115,475 |
kWh
|
$0.063 |
| Electricity Demand | $43,107 | 7,113 |
kW-mo/yr
|
$6.06 |
| Electricity Fees | $4,450 | - |
|
- |
| Natural Gas | $87,064 | 17,399 |
MMBtu
|
$5.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $71,396 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,014 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $813 | $332 |
$273
4,689
kWh
|
$540
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,201 | $1,000 |
$2,784
47,186
kWh
|
$2,279
-
kW-mo/yr
|
$138 | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,386 | $10,530 |
$5,408
77,374
kWh
|
$805
-
kW-mo/yr
|
$173 | - | - | |
| 04 | 2.7496: Install partitions to reduce size of conditioned space | $3,746 | $9,000 | - | - | - |
$3,746
-
MMBtu
|
- | |
| 05 | 4.112: Replace old machine with new automatic multi-station tool | $55,250 | $162,750 | - | - | - | - | $55,250 | |
| TOTAL RECOMMENDED | $71,396 | $183,612 |
$8,465
129,249
kWh
|
$3,624
-
kW-mo/yr
|
$311 |
$3,746
-
MMBtu
|
$55,250 | ||
| TOTAL IMPLEMENTED | $6,014 | $1,332 |
$3,057
51,875
kWh
|
$2,819
-
kW-mo/yr
|
$138 | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs