ITAC Assessment: NV0135
ITAC logo
ITAC Assessment: NV0135
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Concrete Products
NAICS
n/a
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 36,000
ft2
Annual Production 50,000
ton
Production Hrs. Annual 2,210
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,968 1,115,475
kWh
Electricity Demand $43,107 7,113
kW-mo/yr
Electricity Fees $4,450 -
Natural Gas $87,064 17,399
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,396 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,014

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $813 $332 $273
4,689
kWh
$540
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,201 $1,000 $2,784
47,186
kWh
$2,279
-
kW-mo/yr
$138 - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,386 $10,530 $5,408
77,374
kWh
$805
-
kW-mo/yr
$173 - -
04 2.7496: Install partitions to reduce size of conditioned space $3,746 $9,000 - - - $3,746
-
MMBtu
-
05 4.112: Replace old machine with new automatic multi-station tool $55,250 $162,750 - - - - $55,250
TOTAL RECOMMENDED $71,396 $183,612 $8,465
129,249
kWh
$3,624
-
kW-mo/yr
$311 $3,746
-
MMBtu
$55,250
TOTAL IMPLEMENTED $6,014 $1,332 $3,057
51,875
kWh
$2,819
-
kW-mo/yr
$138 - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs