Assessment Year | 2011 |
---|---|
Principal Product | Measurement, Analysis and Control Devices |
NAICS | 334519: Other Measuring and Controlling Device Manufacturing |
SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 494 |
Plant Area |
700,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,960,983 | 16,044,228 |
kWh
|
$0.12 |
Electricity Demand | $162,308 | 40,598 |
kW-mo/yr
|
$4.00 |
Natural Gas | $554,315 | 62,310 |
MMBtu
|
$8.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,154 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,564 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $45,912 | $17,705 |
$16,734
137,162
kWh
|
$29,178
-
MMBtu
|
|
02 | 2.1116: Improve combustion control capability | $31,118 | $100,000 | - |
$31,118
-
MMBtu
|
|
03 | 2.2611: Moderate cooling tower outlet temperature | $11,694 | $10,590 |
$11,694
95,851
kWh
|
- | |
04 | 2.7314: Reduce ventilation air | $8,118 | - |
$4,978
40,800
kWh
|
$3,140
-
MMBtu
|
|
05 | 2.7132: Install timers on light switches in little used areas | $3,023 | $250 |
$3,023
24,780
kWh
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $2,246 | $3,000 |
$2,246
18,414
kWh
|
- | |
07 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,047 | $17,500 |
$5,047
41,368
kWh
|
- | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,129 | $6,340 |
$2,129
17,453
kWh
|
- | |
09 | 2.4323: Use optimum size and capacity equipment | $1,515 | $4,000 |
$1,515
12,414
kWh
|
- | |
10 | 2.1123: Install automatic stack damper | $729 | $180 | - |
$729
-
MMBtu
|
|
11 | 2.2511: Insulate bare equipment | $525 | $550 | - |
$525
-
MMBtu
|
|
12 | 2.2511: Insulate bare equipment | $98 | $201 | - |
$98
-
MMBtu
|
|
TOTAL RECOMMENDED | $112,154 | $160,316 |
$47,366
388,242
kWh
|
$64,788
-
MMBtu
|
||
TOTAL IMPLEMENTED | $23,564 | $11,020 |
$19,695
161,431
kWh
|
$3,869
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs