Assessment Year | 2007 |
---|---|
Principal Product | glass bulbs |
NAICS | 327212: Other Pressed and Blown Glass and Glassware Manufacturing |
SIC | 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
600,000
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 8,341
hrs
|
Location (State) | Rhode Island |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,667,831 | 21,769,461 |
kWh
|
$0.12 |
Electricity Demand | $107,099 | 34,919 |
kW-mo/yr
|
$3.07 |
Electricity Fees | $(-14,827.0) | - |
|
- |
Natural Gas | $1,983,124 | 194,919 |
MMBtu
|
$10.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $133,704 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $133,704 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $47,879 | $79,554 |
$46,191
401,662
kWh
|
$1,688
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $32,820 | $26,621 |
$31,664
275,340
kWh
|
$1,156
-
kW-mo/yr
|
- | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $12,316 | $3,220 | - | - |
$12,316
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,204 | $29,875 |
$11,772
102,363
kWh
|
$432
-
kW-mo/yr
|
- | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $10,589 | $17,740 |
$15,456
134,400
kWh
|
$526
-
kW-mo/yr
|
$(-5,393.0)
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $7,795 | $1,924 |
$7,795
67,779
kWh
|
- | - | |
07 | 2.3212: Optimize plant power factor | $4,906 | $18,500 | - |
$4,906
-
kW-mo/yr
|
- | |
08 | 2.7261: Install timers and/or thermostats | $4,125 | $3,552 |
$1,086
9,445
kWh
|
- |
$3,039
-
MMBtu
|
|
09 | 2.2611: Moderate cooling tower outlet temperature | $1,070 | $340 | - | - |
$1,070
-
MMBtu
|
|
TOTAL RECOMMENDED | $133,704 | $181,326 |
$113,964
990,989
kWh
|
$8,708
-
kW-mo/yr
|
$11,032
-
MMBtu
|
||
TOTAL IMPLEMENTED | $133,704 | $181,326 |
$113,964
990,989
kWh
|
$8,708
-
kW-mo/yr
|
$11,032
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs