Assessment Year | 2007 |
---|---|
Principal Product | Roller Chains |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 177 |
Plant Area |
209,100
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $449,264 | 6,047,433 |
kWh
|
$0.074 |
Electricity Demand | $83,979 | 13,545 |
kW-mo/yr
|
$6.20 |
Electricity Fees | $3,627 | - |
|
- |
Natural Gas | $517,270 | 39,473 |
MMBtu
|
$13.10 |
LPG | $106,138 | 8,274 |
MMBtu
|
$12.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $178,458 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $129,943 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $98,826 | $74,772 |
$(-4,174.0)
(-56,398)
kWh
|
$(-503.0)
-
kW-mo/yr
|
$103,503
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $33,486 | $186,840 |
$28,054
379,100
kWh
|
$5,432
-
kW-mo/yr
|
- | - | |
03 | 2.7314: Reduce ventilation air | $23,954 | $17,587 |
$725
9,797
kWh
|
$121
-
kW-mo/yr
|
$23,108
-
MMBtu
|
- | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $7,443 | $17,876 |
$14,978
202,400
kWh
|
$3,765
-
kW-mo/yr
|
$(-11,300.0)
-
MMBtu
|
- | |
05 | 2.2211: Use optimum temperature | $6,194 | $12,675 | - | - |
$4,834
-
MMBtu
|
$1,360
-
MMBtu
|
|
06 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $3,833 | $5,368 |
$3,833
51,800
kWh
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $3,330 | $3,300 |
$3,330
45,000
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $888 | $6,305 |
$888
12,000
kWh
|
- | - | - | |
09 | 2.7447: Install vinyl strip / high speed / air curtain doors | $504 | $3,600 |
$(-3.0)
(-47)
kWh
|
$(-14.0)
-
kW-mo/yr
|
$521
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $178,458 | $328,323 |
$47,631
643,652
kWh
|
$8,801
-
kW-mo/yr
|
$120,666
-
MMBtu
|
$1,360
-
MMBtu
|
||
TOTAL IMPLEMENTED | $129,943 | $101,027 |
$3,714
50,199
kWh
|
$(-382.0)
-
kW-mo/yr
|
$126,611
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs