| Assessment Year | 2005 |
|---|---|
| Principal Product | Molds for plastic injection industry |
| NAICS | 333511: Industrial Mold Manufacturing |
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $5 M to 10M |
| # of Employees | 62 |
| Plant Area |
53,215
ft2
|
| Annual Production | 250
pieces
|
| Production Hrs. Annual | 5,200
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $134,471 | 1,434,600 |
kWh
|
$0.094 |
| Electricity Demand | $42,834 | 3,929 |
kW-mo/yr
|
$10.90 |
| Natural Gas | $11,940 | 887 |
MMBtu
|
$13.46 |
| Fuel Oil #2 | $400 | 35 |
MMBtu
|
$11.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,617 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,567 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $32,448 | $600 | - | - | - | $32,448 | |
| 02 | 2.8112: Combine utility meters | $4,300 | $15,675 | - | - | $4,300 | - | |
| 03 | 2.7241: Install outside air damper / economizer on hvac unit | $875 | $1,210 |
$875
11,600
kWh
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $1,022 | $1,520 |
$1,022
13,560
kWh
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $580 | $452 |
$430
5,700
kWh
|
$150
-
kW-mo/yr
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $392 | $900 |
$392
5,200
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $39,617 | $20,357 |
$2,719
36,060
kWh
|
$150
-
kW-mo/yr
|
$4,300 | $32,448 | ||
| TOTAL IMPLEMENTED | $5,567 | $17,785 |
$1,267
16,800
kWh
|
- | $4,300 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs