Assessment Year | 2005 |
---|---|
Principal Product | Finished fabric |
NAICS | 313210: Broadwoven Fabric Mills |
SIC | 2221: Broadwoven Fabric Mills, Manmade Fiber and Silk |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
300,000
ft2
|
Annual Production | 33,000
thousand feet
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $441,320 | 5,219,200 |
kWh
|
$0.085 |
Electricity Demand | $72,677 | 16,823 |
kW-mo/yr
|
$4.32 |
Electricity Fees | $(-4,418.0) | - |
|
- |
LPG | $126,207 | 11,218 |
MMBtu
|
$11.25 |
Fuel Oil #6 | $458,811 | 89,856 |
MMBtu
|
$5.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $224,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $224,636 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $75,813 | $205,500 | - | - |
$49,529
-
MMBtu
|
$26,284
-
MMBtu
|
|
02 | 2.1116: Improve combustion control capability | $52,930 | $50,000 | - | - | - |
$52,930
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $46,138 | $58,000 | - | - | - |
$46,138
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $28,600 | $980 | - | - | - |
$28,600
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,371 | $300 |
$14,371
159,500
kWh
|
- | - | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $6,784 | $40,425 |
$(-25,050.0)
(-292,480)
kWh
|
$(-3,915.0)
-
kW-mo/yr
|
$23,363
-
MMBtu
|
$12,386
-
MMBtu
|
|
TOTAL RECOMMENDED | $224,636 | $355,205 |
$(-10,679.0)
(-132,980)
kWh
|
$(-3,915.0)
-
kW-mo/yr
|
$72,892
-
MMBtu
|
$166,338
-
MMBtu
|
||
TOTAL IMPLEMENTED | $224,636 | $355,205 |
$(-10,679.0)
(-132,980)
kWh
|
$(-3,915.0)
-
kW-mo/yr
|
$72,892
-
MMBtu
|
$166,338
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #6 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs