Assessment Year | 2004 |
---|---|
Principal Product | Automotive components |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 267 |
Plant Area |
360,000
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 6,144
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,016,591 | 19,373,978 |
kWh
|
$0.052 |
Electricity Demand | $180,052 | 28,507 |
kW-mo/yr
|
$6.32 |
Natural Gas | $583,933 | 60,486 |
MMBtu
|
$9.65 |
LPG | $94,585 | 11,984 |
MMBtu
|
$7.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $243,653 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $243,653 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $212,625 | $986,100 |
$192,593
2,663,800
kWh
|
$20,032
-
kW-mo/yr
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,690 | $81,637 |
$34,950
483,400
kWh
|
$1,933
-
kW-mo/yr
|
$(-20,193.0)
-
MMBtu
|
- | |
03 | 2.1116: Improve combustion control capability | $1,915 | $44,790 |
$795
11,000
kWh
|
- |
$1,120
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,282 | $5,430 |
$3,282
45,400
kWh
|
- | - | - | |
05 | 2.7261: Install timers and/or thermostats | $2,840 | $500 | - | - | - |
$2,840
-
MMBtu
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,791 | $4,850 |
$2,791
38,600
kWh
|
- | - | - | |
07 | 2.7135: Install occupancy sensors | $1,836 | $768 |
$1,836
25,400
kWh
|
- | - | - | |
08 | 2.7261: Install timers and/or thermostats | $1,139 | $650 | - | - |
$1,139
-
MMBtu
|
- | |
09 | 2.7135: Install occupancy sensors | $535 | $180 |
$535
7,400
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $243,653 | $1,124,905 |
$236,782
3,275,000
kWh
|
$21,965
-
kW-mo/yr
|
$(-17,934.0)
-
MMBtu
|
$2,840
-
MMBtu
|
||
TOTAL IMPLEMENTED | $243,653 | $1,124,905 |
$236,782
3,275,000
kWh
|
$21,965
-
kW-mo/yr
|
$(-17,934.0)
-
MMBtu
|
$2,840
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs