Assessment Year | 2004 |
---|---|
Principal Product | Natural fiber fabric |
NAICS | 313220: Narrow Fabric Mills and Schiffli Machine Embroidery |
SIC | 2241: Narrow Fabric and Other Smallware Mills: Cotton, Wool, Silk, and Manmade Fiber |
Sales Range | $10 M to 50M |
# of Employees | 195 |
Plant Area |
542,304
ft2
|
Annual Production | 5,500
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $450,221 | 8,060,028 |
kWh
|
$0.056 |
Electricity Demand | $213,188 | 23,874 |
kW-mo/yr
|
$8.93 |
Electricity Fees | $(-6,785.0) | - |
|
- |
LPG | $98,707 | 8,475 |
MMBtu
|
$11.65 |
Fuel Oil #2 | $261,229 | 36,265 |
MMBtu
|
$7.20 |
Fuel Oil #6 | $100,211 | 17,270 |
MMBtu
|
$5.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $387,459 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.521: Clear and rent existing space | $200,000 | $398,000 | - | - | - | - | - | $200,000 | |
02 | 2.3322: Use existing dam to generate electricity | $50,195 | $210,000 |
$42,332
774,300
kWh
|
$17,863
-
kW-mo/yr
|
- | - | - | $(-10,000.0) | |
03 | 2.2136: Install / repair insulation on steam lines | $43,010 | $24,670 | - | - | - |
$31,659
-
MMBtu
|
$11,351
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $34,463 | $78,000 |
$2,561
47,600
kWh
|
- | - |
$31,902
-
MMBtu
|
- | - | |
05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $14,711 | $44,000 | - | - | - | - |
$14,711
-
MMBtu
|
- | |
06 | 2.7261: Install timers and/or thermostats | $14,705 | $4,020 | - | - | - | - |
$14,705
-
MMBtu
|
- | |
07 | 2.2163: Use minimum steam operating pressure | $13,419 | - | - | - | - | - |
$13,419
-
MMBtu
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,117 | $6,600 |
$7,117
125,400
kWh
|
- | - | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,321 | $10,950 |
$3,321
54,800
kWh
|
- | - | - | - | - | |
10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,829 | $7,475 |
$1,109
18,300
kWh
|
$2,729
-
kW-mo/yr
|
$(-1,009.0)
-
MMBtu
|
- | - | - | |
11 | 2.7131: Add area lighting switches | $1,964 | $2,400 |
$1,964
36,500
kWh
|
- | - | - | - | - | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,376 | $825 |
$1,376
22,700
kWh
|
- | - | - | - | - | |
13 | 2.2437: Recover waste heat from equipment | $349 | $1,400 | - | - | - |
$349
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $387,459 | $788,340 |
$59,780
1,079,600
kWh
|
$20,592
-
kW-mo/yr
|
$(-1,009.0)
-
MMBtu
|
$63,910
-
MMBtu
|
$54,186
-
MMBtu
|
$190,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs