| Assessment Year | 2003 |
|---|---|
| Principal Product | Large circuit boards |
| NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 407 |
| Plant Area |
214,000
ft2
|
| Annual Production | 420,000
thousand feet
|
| Production Hrs. Annual | 8,424
hrs
|
| Location (State) | New Hampshire |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,834,620 | 22,271,991 |
kWh
|
$0.082 |
| Electricity Demand | $367,805 | 43,021 |
kW-mo/yr
|
$8.55 |
| Electricity Fees | $5,699 | - |
|
- |
| Natural Gas | $680,537 | 109,715 |
MMBtu
|
$6.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $157,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,922 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $89,343 | $700,000 | n/a |
$543,042
8,619,711
kWh
|
$85,000
-
kW-mo/yr
|
$(-495,600.0)
-
MMBtu
|
- | $(-43,099.0) |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,861 | $46,350 |
$24,861
394,620
kWh
|
- | - | - | - | |
| 03 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $14,763 | $14,000 |
$12,383
196,556
kWh
|
$2,380
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $12,264 | $5,500 | - | - |
$12,264
-
MMBtu
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $5,600 | $22,000 | n/a | - | - | - | $5,600 | - |
| 06 | 2.2163: Use minimum steam operating pressure | $5,023 | $5,000 | - | - |
$5,023
-
MMBtu
|
- | - | |
| 07 | 2.6218: Turn off equipment when not in use | $4,751 | - |
$4,751
75,412
kWh
|
- | - | - | - | |
| 08 | 2.2511: Insulate bare equipment | $635 | $260 | - | - |
$635
-
MMBtu
|
- | - | |
| 09 | 2.1213: Direct warmest air to combustion intake | $523 | $72 | - | - |
$523
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $157,763 | $793,182 |
$585,037
9,286,299
kWh
|
$87,380
-
kW-mo/yr
|
$(-477,155.0)
-
MMBtu
|
$5,600 | $(-43,099.0) | ||
| TOTAL IMPLEMENTED | $17,922 | $10,760 | - | - |
$17,922
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs