| Assessment Year | 2002 |
|---|---|
| Principal Product | Matboard products |
| NAICS |
n/a
|
| SIC | 2631: Paperboard Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 95 |
| Plant Area |
152,000
ft2
|
| Annual Production | 12,860
ton
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,306 | 641,714 |
kWh
|
$0.072 |
| Electricity Demand | $19,825 | 2,924 |
kW-mo/yr
|
$6.78 |
| Electricity Fees | $9,037 | - |
|
- |
| Fuel Oil #2 | $52,117 | 7,238 |
MMBtu
|
$7.20 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7229: Air condition only space necessary | $10,201 | $800 | - | - |
$10,201
-
MMBtu
|
|
| 02 | 2.2136: Install / repair insulation on steam lines | $1,687 | $5,159 | - | - |
$1,687
-
MMBtu
|
|
| 03 | 2.6218: Turn off equipment when not in use | $791 | - |
$791
12,376
kWh
|
- | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $582 | $200 |
$362
5,658
kWh
|
$220
-
kW-mo/yr
|
- | |
| 05 | 2.2511: Insulate bare equipment | $425 | $596 | - | - |
$425
-
MMBtu
|
|
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $101 | - |
$101
1,583
kWh
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $80 | $300 |
$80
1,242
kWh
|
- | - | |
| TOTAL RECOMMENDED | $13,867 | $7,055 |
$1,334
20,859
kWh
|
$220
-
kW-mo/yr
|
$12,313
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $12,100 | $1,596 |
$1,254
19,617
kWh
|
$220
-
kW-mo/yr
|
$10,626
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs