ITAC Assessment: MA0525
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Matboard products
NAICS
n/a
SIC 2631: Paperboard Mills
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 152,000
ft2
Annual Production 12,860
ton
Production Hrs. Annual 2,040
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,306 641,714
kWh
Electricity Demand $19,825 2,924
kW-mo/yr
Electricity Fees $9,037 -
Fuel Oil #2 $52,117 7,238
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,867 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings
01 2.7229: Air condition only space necessary $10,201 $800 - - $10,201
-
MMBtu
02 2.2136: Install / repair insulation on steam lines $1,687 $5,159 - - $1,687
-
MMBtu
03 2.6218: Turn off equipment when not in use $791 - $791
12,376
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $582 $200 $362
5,658
kWh
$220
-
kW-mo/yr
-
05 2.2511: Insulate bare equipment $425 $596 - - $425
-
MMBtu
06 2.6212: Turn off equipment during breaks, reduce operating time $101 - $101
1,583
kWh
- -
07 2.4221: Install compressor air intakes in coolest locations $80 $300 $80
1,242
kWh
- -
TOTAL RECOMMENDED $13,867 $7,055 $1,334
20,859
kWh
$220
-
kW-mo/yr
$12,313
-
MMBtu
TOTAL IMPLEMENTED $12,100 $1,596 $1,254
19,617
kWh
$220
-
kW-mo/yr
$10,626
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs