| Assessment Year | 2002 |
|---|---|
| Principal Product | Face and Paving Brick |
| NAICS |
n/a
|
| SIC | 3251: Brick and Structural Clay Tile |
| Sales Range | $10 M to 50M |
| # of Employees | 53 |
| Plant Area |
167,070
ft2
|
| Annual Production | 51,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $263,834 | 4,962,960 |
kWh
|
$0.053 |
| Electricity Demand | $93,046 | 12,000 |
kW-mo/yr
|
$7.75 |
| Electricity Fees | $6,217 | - |
|
- |
| Natural Gas | $1,112,460 | 191,905 |
MMBtu
|
$5.80 |
| LPG | $6,013 | 444 |
MMBtu
|
$13.54 |
| Other Energy | $6,980 | 231 |
MMBtu
|
$30.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,811 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $21,321 | $60,800 | - | - |
$21,321
-
MMBtu
|
- | |
| 02 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $18,790 | $45,905 | - | - |
$18,790
-
MMBtu
|
- | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $4,396 | - | - | - |
$4,396
-
MMBtu
|
- | |
| 04 | 2.6242: Minimize operation of equipment maintained in standby condition | $3,396 | $4,200 |
$3,396
57,645
kWh
|
- | - | - | |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $2,790 | $1,200 | - | - | - |
$2,790
-
MMBtu
|
|
| 06 | 2.4221: Install compressor air intakes in coolest locations | $439 | $1,600 |
$439
7,454
kWh
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $230 | $608 |
$230
3,898
kWh
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $161 | $4,560 |
$125
2,115
kWh
|
$36
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $51,523 | $118,873 |
$4,190
71,112
kWh
|
$36
-
kW-mo/yr
|
$44,507
-
MMBtu
|
$2,790
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,811 | $52,905 |
$3,835
65,099
kWh
|
- |
$23,186
-
MMBtu
|
$2,790
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs